پروژه = SR6Exhaust.mpp
| WBS | taskname | duration | duration | تاریخ | start | تاریخ | finish | predecessors | persianstart | persianfinish | physicalcomplete | complete | planprogress | actualprogress | cost | resource | WF | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | امكان سنجي و توجيه اقتصادي پروژه | 0 | 0 | 2025/05/01 | May 1 2025 8:00AM | 2025/05/01 | May 1 2025 8:00AM | 1404/2/11 | 1404/2/11 | 0 | 100 | 0 | 0 | 0 | مسئول پروژه ( آقاي رضائي فرد)/كنترل پروژه[0%] | 0 | Edit Details Delete | |
| 2 | شروع پروژه | 0 | 0 | 2025/05/01 | May 1 2025 8:00AM | 2025/05/01 | May 1 2025 8:00AM | 1 | 1404/2/11 | 1404/2/11 | 0 | 100 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 3 | فاز مهندسي | 43 | 0 | 2025/05/01 | May 1 2025 8:00AM | 2025/06/29 | Jun 29 2025 12:00PM | 1 | 1404/2/11 | 1404/4/8 | 0 | 100 | 7.17 | 4.32 | 0 | 7.17 | Edit Details Delete | |
| 3.1 | دريافت اطلاعات فني از مشتري (نقشه، شناسنامه فني ، تست پلن و ...) | 7 | 0 | 2025/05/01 | May 1 2025 8:00AM | 2025/05/10 | May 10 2025 5:00PM | 1SS | 1404/2/11 | 1404/2/20 | 50 | 100 | 1.32 | 0.66 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 1.32 | Edit Details Delete |
| 3.2 | دريافت نمونه اگزوز وارداتي ( مجموعه كامل) | 2 | 0 | 2025/06/03 | Jun 3 2025 8:00AM | 2025/06/04 | Jun 4 2025 5:00PM | 1SS | 1404/3/13 | 1404/3/14 | 100 | 100 | 0.38 | 0.38 | 0 | مهندسي پروژه ( آقاي يعقوبي) | 0.38 | Edit Details Delete |
| 3.3 | دريافت نمونه اگزوز وارداتي (منفصله ) | 7 | 0 | 2025/05/01 | May 1 2025 8:00AM | 2025/05/10 | May 10 2025 5:00PM | 1SS | 1404/2/11 | 1404/2/20 | 100 | 100 | 1.32 | 1.32 | 0 | مهندسي پروژه ( آقاي يعقوبي) | 1.32 | Edit Details Delete |
| 3.4 | spl /Bomتهيه اوليه | 5 | 0 | 2025/06/07 | Jun 7 2025 8:00AM | 2025/06/11 | Jun 11 2025 5:00PM | 5,4 | 1404/3/17 | 1404/3/21 | 50 | 100 | 0.94 | 0.47 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.94 | Edit Details Delete |
| 3.5 | اسكن اگزوز دريافتي | 14 | 0 | 2025/06/07 | Jun 7 2025 8:00AM | 2025/06/24 | Jun 24 2025 5:00PM | 5 | 1404/3/17 | 1404/4/3 | 50 | 100 | 2.64 | 1.32 | 0 | بازرگاني ( آقاي مرادي) | 2.64 | Edit Details Delete |
| 3.6 | بررسي نمونه دريافتي با نقشه هاو اعلام مغايرت ها /bom | 2 | 0 | 2025/06/25 | Jun 25 2025 8:00AM | 2025/06/28 | Jun 28 2025 12:00PM | 4,8 | 1404/4/4 | 1404/4/7 | 20 | 100 | 0.38 | 0.08 | 0 | مسئول پروژه ( آقاي رضائي فرد) | 0.38 | Edit Details Delete |
| 3.7 | تهيه و ارسال نقشه هاي اگزوز به واحد بازرگاني | 1 | 0 | 2025/06/28 | Jun 28 2025 1:00PM | 2025/06/29 | Jun 29 2025 12:00PM | 9 | 1404/4/7 | 1404/4/8 | 50 | 100 | 0.19 | 0.09 | 0 | مهندسي پروژه ( آقاي يعقوبي) | 0.19 | Edit Details Delete |
| 3.8 | پايان فاز مهندسي | 0 | 0 | 2025/06/29 | Jun 29 2025 12:00PM | 2025/06/29 | Jun 29 2025 12:00PM | 4,5,7,9,10 | 1404/4/8 | 1404/4/8 | 0 | 100 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 4 | فاز تامين و قالب سازي | 61 | 0 | 2025/06/07 | Jun 7 2025 8:00AM | 2025/08/25 | Aug 25 2025 5:00PM | 1404/3/17 | 1404/6/3 | 0 | 32 | 15.09 | 4.91 | 0 | 47.17 | Edit Details Delete | ||
| 4.1 | نمونه مقدماتي اگزوزبا منبع ،لوله و هنگر | 61 | 0 | 2025/06/07 | Jun 7 2025 8:00AM | 2025/08/25 | Aug 25 2025 5:00PM | 1404/3/17 | 1404/6/3 | 0 | 41 | 4.72 | 3.96 | 0 | 11.51 | Edit Details Delete | ||
| 4.1.1 | انتخاب پيمانكار | 5 | 0 | 2025/06/07 | Jun 7 2025 8:00AM | 2025/06/11 | Jun 11 2025 5:00PM | 5 | 1404/3/17 | 1404/3/21 | 100 | 100 | 0.94 | 0.94 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.94 | Edit Details Delete |
| 4.1.2 | مذاکره با پیمانکار جهت بررسي و ساخت اگزوز | 16 | 0 | 2025/06/12 | Jun 12 2025 8:00AM | 2025/07/03 | Jul 3 2025 5:00PM | 14 | 1404/3/22 | 1404/4/12 | 100 | 100 | 3.02 | 3.02 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 3.02 | Edit Details Delete |
| 4.1.3 | توليد 5 ست بعنوان نمونه اوليه | 35 | 0 | 2025/07/06 | Jul 6 2025 8:00AM | 2025/08/19 | Aug 19 2025 12:00PM | 15 | 1404/4/15 | 1404/5/28 | 0 | 11 | 0.73 | 0 | 0 | تامين كننده ( ايران اگزوز ) | 6.6 | Edit Details Delete |
| 4.1.4 | ارسال نمونه هاي اوليه به كارخانه | 5 | 0 | 2025/08/19 | Aug 19 2025 1:00PM | 2025/08/25 | Aug 25 2025 5:00PM | 16 | 1404/5/28 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( ايران اگزوز ) | 0.94 | Edit Details Delete |
| 4.2 | GPF | 18 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/22 | Jul 22 2025 5:00PM | 1404/4/8 | 1404/4/31 | 0 | 62 | 3.04 | 0 | 0 | 4.91 | Edit Details Delete | ||
| 4.2.1 | X5 توليدقطعات مشابه كاتاباكس(عايق حرارت گير ، شيپوري و براكت ) | 15 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/19 | Jul 19 2025 5:00PM | 10 | 1404/4/8 | 1404/4/28 | 0 | 53 | 1.5 | 0 | 0 | تامين كننده كاراحديد نامي | 2.83 | Edit Details Delete |
| 4.2.2 | سفارشگذاري و توليد پوسته | 1 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/06/30 | Jun 30 2025 12:00PM | 10 | 1404/4/8 | 1404/4/9 | 0 | 100 | 0.19 | 0 | 0 | آريا پاك مبدل | 0.19 | Edit Details Delete |
| 4.2.3 | تامين مهره و پيچ جوشي براكت | 7 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/08 | Jul 8 2025 5:00PM | 10 | 1404/4/8 | 1404/4/17 | 0 | 100 | 1.32 | 0 | 0 | سازنده مشخص نشده | 1.32 | Edit Details Delete |
| 4.2.4 | ارسال قطعات توليدي به بم | 3 | 0 | 2025/07/20 | Jul 20 2025 8:00AM | 2025/07/22 | Jul 22 2025 5:00PM | 19,21,20 | 1404/4/29 | 1404/4/31 | 0 | 0 | 0 | 0 | 0 | تامين كننده كاراحديد نامي | 0.57 | Edit Details Delete |
| 4.3 | سر اگزوز | 44 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/08/25 | Aug 25 2025 5:00PM | 1404/4/8 | 1404/6/3 | 0 | 18 | 1.49 | 0 | 0 | 8.3 | Edit Details Delete | ||
| 4.3.1 | انتخاب پيمانكار ساخت قالب | 5 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/06 | Jul 6 2025 5:00PM | 10,6 | 1404/4/8 | 1404/4/15 | 0 | 100 | 0.94 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.94 | Edit Details Delete |
| 4.3.2 | عقد قرارداد و پيش پرداخت | 5 | 0 | 2025/07/07 | Jul 7 2025 8:00AM | 2025/07/13 | Jul 13 2025 12:00PM | 24 | 1404/4/16 | 1404/4/22 | 0 | 60 | 0.57 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.94 | Edit Details Delete |
| 4.3.3 | ساخت قالب ها | 30 | 0 | 2025/07/13 | Jul 13 2025 1:00PM | 2025/08/20 | Aug 20 2025 12:00PM | 25 | 1404/4/22 | 1404/5/29 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( افرا كوشا فدك) | 5.66 | Edit Details Delete |
| 4.3.4 | توليد نمونه | 2 | 0 | 2025/08/20 | Aug 20 2025 1:00PM | 2025/08/23 | Aug 23 2025 5:00PM | 26 | 1404/5/29 | 1404/6/1 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( افرا كوشا فدك) | 0.38 | Edit Details Delete |
| 4.3.5 | تائيديه قالب و نمونه | 2 | 0 | 2025/08/24 | Aug 24 2025 8:00AM | 2025/08/25 | Aug 25 2025 5:00PM | 27 | 1404/6/2 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | مسئول پروژه ( آقاي رضائي فرد) | 0.38 | Edit Details Delete |
| 4.4 | Pipe قالبسازي براكت | 44 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/08/25 | Aug 25 2025 5:00PM | 1404/4/8 | 1404/6/3 | 0 | 18 | 1.49 | 0 | 0 | 8.3 | Edit Details Delete | ||
| 4.4.1 | انتخاب پيمانكار ساخت قالب | 5 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/06 | Jul 6 2025 5:00PM | 10,6 | 1404/4/8 | 1404/4/15 | 0 | 100 | 0.94 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.94 | Edit Details Delete |
| 4.4.2 | عقد قرارداد و پيش پرداخت | 2 | 0 | 2025/07/07 | Jul 7 2025 8:00AM | 2025/07/08 | Jul 8 2025 5:00PM | 30 | 1404/4/16 | 1404/4/17 | 0 | 100 | 0.38 | 0 | 0 | سازنده قالب نهائي نشده | 0.38 | Edit Details Delete |
| 4.4.3 | ساخت قالب ها | 34 | 0 | 2025/07/09 | Jul 9 2025 8:00AM | 2025/08/21 | Aug 21 2025 12:00PM | 31 | 1404/4/18 | 1404/5/30 | 0 | 3 | 0.19 | 0 | 0 | سازنده قالب نهائي نشده | 6.42 | Edit Details Delete |
| 4.4.4 | توليد نمونه | 2 | 0 | 2025/08/23 | Aug 23 2025 8:00AM | 2025/08/24 | Aug 24 2025 5:00PM | 32 | 1404/6/1 | 1404/6/2 | 0 | 0 | 0 | 0 | 0 | سازنده قالب نهائي نشده | 0.38 | Edit Details Delete |
| 4.4.5 | تائيديه قالب و نمونه | 1 | 0 | 2025/08/25 | Aug 25 2025 8:00AM | 2025/08/25 | Aug 25 2025 5:00PM | 33 | 1404/6/3 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | سازنده قالب نهائي نشده | 0.19 | Edit Details Delete |
| 4.5 | مهره سنسور فشار و دما ( مشترك X5-J7-SR6) | 30 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/08/06 | Aug 6 2025 5:00PM | 1404/4/8 | 1404/5/15 | 0 | 27 | 1.53 | 0 | 0 | 5.66 | Edit Details Delete | ||
| 4.5.1 | انتخاب تراشكار | 7 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/08 | Jul 8 2025 5:00PM | 10 | 1404/4/8 | 1404/4/17 | 0 | 100 | 1.32 | 0 | 0 | ماشين كار مشخص نشده است | 1.32 | Edit Details Delete |
| 4.5.2 | عقد قرارداد و پيش پرداخت | 2 | 0 | 2025/07/09 | Jul 9 2025 8:00AM | 2025/07/12 | Jul 12 2025 12:00PM | 36 | 1404/4/18 | 1404/4/21 | 0 | 50 | 0.19 | 0 | 0 | ماشين كار مشخص نشده است | 0.38 | Edit Details Delete |
| 4.5.3 | توليد نمونه | 20 | 0 | 2025/07/12 | Jul 12 2025 1:00PM | 2025/08/05 | Aug 5 2025 5:00PM | 37 | 1404/4/21 | 1404/5/14 | 0 | 0 | 0 | 0 | 0 | ماشين كار مشخص نشده است | 3.77 | Edit Details Delete |
| 4.5.4 | تائيديه نمونه | 1 | 0 | 2025/08/06 | Aug 6 2025 8:00AM | 2025/08/06 | Aug 6 2025 5:00PM | 38 | 1404/5/15 | 1404/5/15 | 0 | 0 | 0 | 0 | 0 | ماشين كار مشخص نشده است | 0.19 | Edit Details Delete |
| 4.6 | منجيد(مشابه ) | 10 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/13 | Jul 13 2025 12:00PM | 1404/4/8 | 1404/4/22 | 0 | 80 | 1.51 | 0.94 | 0 | 1.89 | Edit Details Delete | ||
| 4.6.1 | تامين منجيد دو سوراخ | 10 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/07/13 | Jul 13 2025 12:00PM | 10 | 1404/4/8 | 1404/4/22 | 50 | 80 | 1.51 | 0.94 | 0 | آذين پليمر/ بازرگاني(آقاي صفائي) | 1.89 | Edit Details Delete |
| 4.7 | مت و منوليت | 35 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/08/13 | Aug 13 2025 12:00PM | 1404/4/8 | 1404/5/22 | 0 | 23 | 1.52 | 0 | 0 | 6.6 | Edit Details Delete | ||
| 4.7.1 | سفارش گذاري براي پك ckd مت منوليت | 35 | 0 | 2025/06/29 | Jun 29 2025 1:00PM | 2025/08/13 | Aug 13 2025 12:00PM | 10 | 1404/4/8 | 1404/5/22 | 0 | 23 | 1.52 | 0 | 0 | بازرگاني خارجي ( آقاي محمودي) | 6.6 | Edit Details Delete |
| 4.8 | پايان تامين و قالب سازي | 0 | 0 | 2025/08/25 | Aug 25 2025 5:00PM | 2025/08/25 | Aug 25 2025 5:00PM | 22,17,28,34,39,41,43 | 1404/6/3 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 5 | فاز نمونه اوليه وساخت فيكسچر | 98 | 0 | 2025/08/26 | Aug 26 2025 8:00AM | 2025/12/31 | Dec 31 2025 5:00PM | 1404/6/4 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | 32.83 | Edit Details Delete | ||
| 5.1 | توليد 5 عدد مجموعه اگزوز اوليه | 2 | 0 | 2025/08/26 | Aug 26 2025 8:00AM | 2025/08/27 | Aug 27 2025 5:00PM | 17,44 | 1404/6/4 | 1404/6/5 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول ( آقاي غضنفري) | 0.38 | Edit Details Delete |
| 5.2 | تحويل به مهندسي محصول كرمان موتور جهت بررسي | 3 | 0 | 2025/08/28 | Aug 28 2025 8:00AM | 2025/09/02 | Sep 2 2025 12:00PM | 46 | 1404/6/6 | 1404/6/11 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول ( آقاي غضنفري)/مهندسي محصول كرمان موتور ( آقاي تيرگر) | 0.57 | Edit Details Delete |
| 5.3 | ثبت كارتابل نمونه اوليه | 2 | 0 | 2025/09/02 | Sep 2 2025 1:00PM | 2025/09/04 | Sep 4 2025 12:00PM | 47 | 1404/6/11 | 1404/6/13 | 0 | 0 | 0 | 0 | 0 | كادك ( خانم معافي) | 0.38 | Edit Details Delete |
| 5.4 | اخذ تاييديه نمونه اوليه | 10 | 0 | 2025/09/06 | Sep 6 2025 8:00AM | 2025/09/18 | Sep 18 2025 12:00PM | 1404/6/15 | 1404/6/27 | 0 | 0 | 0 | 0 | 0 | 1.89 | Edit Details Delete | ||
| 5.4.1 | انجام تست هاي مونتاژ پذيري در بم | 5 | 0 | 2025/09/06 | Sep 6 2025 8:00AM | 2025/09/13 | Sep 13 2025 12:00PM | 48 | 1404/6/15 | 1404/6/22 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 0.94 | Edit Details Delete |
| 5.4.2 | ارسال گزارش | 2 | 0 | 2025/09/13 | Sep 13 2025 1:00PM | 2025/09/15 | Sep 15 2025 12:00PM | 50 | 1404/6/22 | 1404/6/24 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 0.38 | Edit Details Delete |
| 5.4.3 | اخذ تائيديه | 3 | 0 | 2025/09/15 | Sep 15 2025 1:00PM | 2025/09/18 | Sep 18 2025 12:00PM | 51 | 1404/6/24 | 1404/6/27 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.57 | Edit Details Delete |
| 5.5 | تهيه نهايي BOM | 2 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2025/09/21 | Sep 21 2025 5:00PM | 52 | 1404/6/29 | 1404/6/30 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول( خانم فرامرز پور) | 0.38 | Edit Details Delete |
| 5.6 | آدیت تضمین کیفیت | 1 | 0 | 2025/09/22 | Sep 22 2025 8:00AM | 2025/09/22 | Sep 22 2025 5:00PM | 53,52 | 1404/6/31 | 1404/6/31 | 0 | 0 | 0 | 0 | 0 | تضمين كيفيت ( آقاي جلال الديني) | 0.19 | Edit Details Delete |
| 5.7 | تست آلايندگي | 50 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2025/11/22 | Nov 22 2025 12:00PM | 1404/6/29 | 1404/9/1 | 0 | 0 | 0 | 0 | 0 | 9.43 | Edit Details Delete | ||
| 5.7.1 | ارسال نمونه به تهران جهت ارسال به كرمان موتور براي انجام تست | 3 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2025/09/22 | Sep 22 2025 5:00PM | 52 | 1404/6/29 | 1404/6/31 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 0.57 | Edit Details Delete |
| 5.7.2 | تست آلايندگي و تست توان سر چرخ نمونه مطالعاتی | 45 | 0 | 2025/09/23 | Sep 23 2025 8:00AM | 2025/11/18 | Nov 18 2025 5:00PM | 56 | 1404/7/1 | 1404/8/27 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 8.49 | Edit Details Delete |
| 5.7.3 | ارسال نتايج به آرمان موتور جهت ثبت در آرشيو فني | 2 | 0 | 2025/11/19 | Nov 19 2025 8:00AM | 2025/11/22 | Nov 22 2025 12:00PM | 57 | 1404/8/28 | 1404/9/1 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.38 | Edit Details Delete |
| 5.8 | فيكسچرهاي توليدي وكنترلي | 81 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2025/12/31 | Dec 31 2025 5:00PM | 1404/6/29 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | 19.62 | Edit Details Delete | ||
| 5.8.1 | طراحي فيكسچر | 29 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2025/10/26 | Oct 26 2025 12:00PM | 1404/6/29 | 1404/8/4 | 0 | 0 | 0 | 0 | 0 | 5.47 | Edit Details Delete | ||
| 5.8.1.1 | اسكن نمونه تائيد شده و مدلسازي | 14 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2025/10/06 | Oct 6 2025 5:00PM | 52 | 1404/6/29 | 1404/7/14 | 0 | 0 | 0 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 2.64 | Edit Details Delete |
| 5.8.1.2 | طراحي فيكسچر توليدي و كنترلي | 10 | 0 | 2025/10/07 | Oct 7 2025 8:00AM | 2025/10/19 | Oct 19 2025 5:00PM | 61 | 1404/7/15 | 1404/7/27 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي يوسفيان) | 1.89 | Edit Details Delete |
| 5.8.1.3 | اخذ تائيديه براي فيكسچرهاي كنترلي مجموعه نهايي از كادك | 5 | 0 | 2025/10/20 | Oct 20 2025 8:00AM | 2025/10/26 | Oct 26 2025 12:00PM | 62 | 1404/7/28 | 1404/8/4 | 0 | 0 | 0 | 0 | 0 | الزامات كادك ( آقاي صالحي) | 0.94 | Edit Details Delete |
| 5.8.2 | ساخت فيكسچرتوليدي | 23 | 0 | 2025/10/26 | Oct 26 2025 1:00PM | 2025/11/25 | Nov 25 2025 12:00PM | 1404/8/4 | 1404/9/4 | 0 | 0 | 0 | 0 | 0 | 4.34 | Edit Details Delete | ||
| 5.8.2.1 | ليزر برش قطعات فيكسچر توليدي | 15 | 0 | 2025/10/26 | Oct 26 2025 1:00PM | 2025/11/13 | Nov 13 2025 12:00PM | 63 | 1404/8/4 | 1404/8/22 | 0 | 0 | 0 | 0 | 0 | سازنده مشخص نشده | 2.83 | Edit Details Delete |
| 5.8.2.2 | ارسال فيكسچر به بم | 3 | 0 | 2025/11/15 | Nov 15 2025 8:00AM | 2025/11/17 | Nov 17 2025 5:00PM | 65 | 1404/8/24 | 1404/8/26 | 0 | 0 | 0 | 0 | 0 | بازرگاني ( آقاي مرادي),مهندسي پروژه ( آقاي يوسفيان) | 0.57 | Edit Details Delete |
| 5.8.2.3 | مونتاژ فيكسچر هاي توليدي در كارخانه | 5 | 0 | 2025/11/18 | Nov 18 2025 8:00AM | 2025/11/25 | Nov 25 2025 12:00PM | 66 | 1404/8/27 | 1404/9/4 | 0 | 0 | 0 | 0 | 0 | مهندسي ابزار(آقاي ترك پور) | 0.94 | Edit Details Delete |
| 5.8.3 | ساخت فيكسچركنترلي | 50 | 0 | 2025/10/26 | Oct 26 2025 1:00PM | 2025/12/29 | Dec 29 2025 5:00PM | 1404/8/4 | 1404/10/8 | 0 | 0 | 0 | 0 | 0 | 9.43 | Edit Details Delete | ||
| 5.8.3.1 | ساخت فيكسچرهاي كنترلي | 45 | 0 | 2025/10/26 | Oct 26 2025 1:00PM | 2025/12/23 | Dec 23 2025 12:00PM | 62,63 | 1404/8/4 | 1404/10/2 | 0 | 0 | 0 | 0 | 0 | سازنده مشخص نشده | 8.49 | Edit Details Delete |
| 5.8.3.2 | گزارش گيري ابعادي/ cmm | 2 | 0 | 2025/12/23 | Dec 23 2025 1:00PM | 2025/12/25 | Dec 25 2025 12:00PM | 69 | 1404/10/2 | 1404/10/4 | 0 | 0 | 0 | 0 | 0 | سازنده مشخص نشده | 0.38 | Edit Details Delete |
| 5.8.3.3 | ارسال فيكسچر به بم | 3 | 0 | 2025/12/27 | Dec 27 2025 8:00AM | 2025/12/29 | Dec 29 2025 5:00PM | 70 | 1404/10/6 | 1404/10/8 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي يوسفيان),بازرگاني ( آقاي مرادي) | 0.57 | Edit Details Delete |
| 5.8.4 | صورتجلسه تائيد و تحويل فيكسچرها به واحد توليد | 2 | 0 | 2025/12/30 | Dec 30 2025 8:00AM | 2025/12/31 | Dec 31 2025 5:00PM | 67,71 | 1404/10/9 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي يوسفيان),مهندسي ابزار(آقاي ترك پور) | 0.38 | Edit Details Delete |
| 5.9 | پايان فاز | 0 | 0 | 2025/12/31 | Dec 31 2025 5:00PM | 2025/12/31 | Dec 31 2025 5:00PM | 52,58,67,63,71,72 | 1404/10/10 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 6 | فاز يك روز خط | 87 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2026/01/08 | Jan 8 2026 12:00PM | 1404/6/29 | 1404/10/18 | 0 | 0 | 0 | 0 | 0 | 12.83 | Edit Details Delete | ||
| 6.1 | سفارش گذاري 100 ست | 5 | 0 | 2025/09/20 | Sep 20 2025 8:00AM | 2025/09/24 | Sep 24 2025 5:00PM | 49,52 | 1404/6/29 | 1404/7/2 | 0 | 0 | 0 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.94 | Edit Details Delete |
| 6.2 | توليد و ارسال قطعات يك روز خط به كارخانه | 10 | 0 | 2025/09/25 | Sep 25 2025 8:00AM | 2025/10/07 | Oct 7 2025 5:00PM | 75 | 1404/7/3 | 1404/7/15 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( ايران اگزوز ) | 1.89 | Edit Details Delete |
| 6.3 | آديت فرآيند واحد تضمين كيفيت | 1 | 0 | 2025/10/08 | Oct 8 2025 8:00AM | 2025/10/08 | Oct 8 2025 5:00PM | 76 | 1404/7/16 | 1404/7/16 | 0 | 0 | 0 | 0 | 0 | تضمين كيفيت ( آقاي جلال الديني) | 0.19 | Edit Details Delete |
| 6.4 | توليد يك روز خط اگزوز در آرمان موتور | 4 | 0 | 2025/11/25 | Nov 25 2025 1:00PM | 2025/11/30 | Nov 30 2025 5:00PM | 77SS,76,67 | 1404/9/4 | 1404/9/9 | 0 | 0 | 0 | 0 | 0 | مهندسي توليد /مهندسي پروژه | 0.75 | Edit Details Delete |
| 6.5 | ثبت كارتابل يك روز خط و ارسال قطعات به خط توليد كرمان موتور | 3 | 0 | 2025/12/01 | Dec 1 2025 8:00AM | 2025/12/03 | Dec 3 2025 5:00PM | 78 | 1404/9/10 | 1404/9/12 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.57 | Edit Details Delete |
| 6.6 | مونتاژ يك روز خط-بسته به برنامه توليد | 3 | 0 | 2025/12/04 | Dec 4 2025 8:00AM | 2025/12/08 | Dec 8 2025 12:00PM | 79 | 1404/9/13 | 1404/9/17 | 0 | 0 | 0 | 0 | 0 | مهندسي توليد /مهندسي پروژه | 0.57 | Edit Details Delete |
| 6.7 | ارزيابي يك روز خط | 4 | 0 | 2026/01/01 | Jan 1 2026 8:00AM | 2026/01/06 | Jan 6 2026 12:00PM | 80,73 | 1404/10/11 | 1404/10/16 | 0 | 0 | 0 | 0 | 0 | كادك ( آقاي عبدي) | 0.75 | Edit Details Delete |
| 6.8 | تاييديه يك روز خط | 2 | 0 | 2026/01/06 | Jan 6 2026 1:00PM | 2026/01/08 | Jan 8 2026 12:00PM | 81 | 1404/10/16 | 1404/10/18 | 0 | 0 | 0 | 0 | 0 | كادك ( آقاي عبدي) | 0.38 | Edit Details Delete |
| 6.9 | انجام تست هاي ذكر شده در تست پلن، تهيه تست ريپورت | 36 | 0 | 2025/11/22 | Nov 22 2025 1:00PM | 2026/01/07 | Jan 7 2026 12:00PM | 1404/9/1 | 1404/10/17 | 0 | 0 | 0 | 0 | 0 | 6.79 | Edit Details Delete | ||
| 6.9.1 | دريافت پيش فاكتور از آزمايشگاه | 2 | 0 | 2025/11/22 | Nov 22 2025 1:00PM | 2025/11/25 | Nov 25 2025 12:00PM | 58 | 1404/9/1 | 1404/9/4 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.38 | Edit Details Delete |
| 6.9.2 | پرداخت مبلغ انجام تست | 2 | 0 | 2025/11/25 | Nov 25 2025 1:00PM | 2025/11/27 | Nov 27 2025 12:00PM | 84 | 1404/9/4 | 1404/9/6 | 0 | 0 | 0 | 0 | 0 | خزانه ( آقاي محمودي) | 0.38 | Edit Details Delete |
| 6.9.3 | ارسال قطعات به ازمايشگاه | 2 | 0 | 2025/11/29 | Nov 29 2025 8:00AM | 2025/11/30 | Nov 30 2025 5:00PM | 85 | 1404/9/8 | 1404/9/9 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.38 | Edit Details Delete |
| 6.9.4 | انجام آزمون و تهيه تست ريپورت | 30 | 0 | 2025/12/01 | Dec 1 2025 8:00AM | 2026/01/07 | Jan 7 2026 12:00PM | 86 | 1404/9/10 | 1404/10/17 | 0 | 0 | 0 | 0 | 0 | آزمايشگاه مشخص نيست | 5.66 | Edit Details Delete |
| 7 | اتمام پروژه- سفارشگذاري جهت توليد انبوه | 0 | 0 | 2026/01/08 | Jan 8 2026 12:00PM | 2026/01/08 | Jan 8 2026 12:00PM | 82,83 | 1404/10/18 | 1404/10/18 | 0 | 0 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 0 | Exhaust-SR6 | 191.5d | 0.0d | 2025/05/01 | 5/1/2025 12:00:00 AM | 2026/01/08 | 1/8/2026 12:00:00 AM | 1404/2/11 | 1404/10/18 | 0 | 22 | 21.999999999999996 | 9.226415094339623 | 0 | 99.99999999999997 | Edit Details Delete | ||
| 1 | امكان سنجي و توجيه اقتصادي پروژه | 0.0d | 0.0d | 2025/05/01 | 5/1/2025 12:00:00 AM | 2025/05/01 | 5/1/2025 12:00:00 AM | 1404/2/11 | 1404/2/11 | 0 | 100 | 0 | 0 | 0 | مسئول پروژه ( آقاي رضائي فرد)/كنترل پروژه | 0 | Edit Details Delete | |
| 2 | شروع پروژه | 0.0d | 0.0d | 2025/05/01 | 5/1/2025 12:00:00 AM | 2025/05/01 | 5/1/2025 12:00:00 AM | 1 | 1404/2/11 | 1404/2/11 | 0 | 100 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 3 | فاز مهندسي | 43.5d | 0.0d | 2025/05/01 | 5/1/2025 12:00:00 AM | 2025/06/29 | 6/29/2025 12:00:00 AM | 1 | 1404/2/11 | 1404/4/8 | 0 | 100 | 7.169811320754718 | 4.320754716981132 | 0 | 7.169811320754718 | Edit Details Delete | |
| 3.1 | دريافت اطلاعات فني از مشتري (نقشه، شناسنامه فني ، تست پلن و ...) | 7.0d | 7.0d | 2025/05/01 | 5/1/2025 12:00:00 AM | 2025/05/10 | 5/10/2025 12:00:00 AM | 1 | 1404/2/11 | 1404/2/20 | 50 | 100 | 1.3207547169811322 | 0.6603773584905661 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 1.3207547169811322 | Edit Details Delete |
| 3.2 | دريافت نمونه اگزوز وارداتي ( مجموعه كامل) | 2.0d | 2.0d | 2025/06/03 | 6/3/2025 12:00:00 AM | 2025/06/04 | 6/4/2025 12:00:00 AM | 1 | 1404/3/13 | 1404/3/14 | 100 | 100 | 0.37735849056603776 | 0.37735849056603776 | 0 | مهندسي پروژه ( آقاي يعقوبي) | 0.37735849056603776 | Edit Details Delete |
| 3.3 | دريافت نمونه اگزوز وارداتي (منفصله ) | 7.0d | 7.0d | 2025/05/01 | 5/1/2025 12:00:00 AM | 2025/05/10 | 5/10/2025 12:00:00 AM | 1 | 1404/2/11 | 1404/2/20 | 100 | 100 | 1.3207547169811322 | 1.3207547169811322 | 0 | مهندسي پروژه ( آقاي يعقوبي) | 1.3207547169811322 | Edit Details Delete |
| 3.4 | spl /Bomتهيه اوليه | 5.0d | 5.0d | 2025/06/07 | 6/7/2025 12:00:00 AM | 2025/06/11 | 6/11/2025 12:00:00 AM | 5,4 | 1404/3/17 | 1404/3/21 | 50 | 100 | 0.9433962264150944 | 0.4716981132075472 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.9433962264150944 | Edit Details Delete |
| 3.5 | اسكن اگزوز دريافتي | 14.0d | 14.0d | 2025/06/07 | 6/7/2025 12:00:00 AM | 2025/06/24 | 6/24/2025 12:00:00 AM | 5 | 1404/3/17 | 1404/4/3 | 50 | 100 | 2.6415094339622645 | 1.3207547169811322 | 0 | بازرگاني ( آقاي مرادي) | 2.6415094339622645 | Edit Details Delete |
| 3.6 | بررسي نمونه دريافتي با نقشه هاو اعلام مغايرت ها /bom | 2.0d | 2.0d | 2025/06/25 | 6/25/2025 12:00:00 AM | 2025/06/28 | 6/28/2025 12:00:00 AM | 4,8 | 1404/4/4 | 1404/4/7 | 20 | 100 | 0.37735849056603776 | 0.07547169811320754 | 0 | مسئول پروژه ( آقاي رضائي فرد) | 0.37735849056603776 | Edit Details Delete |
| 3.7 | تهيه و ارسال نقشه هاي اگزوز به واحد بازرگاني | 1.0d | 1.0d | 2025/06/28 | 6/28/2025 12:00:00 AM | 2025/06/29 | 6/29/2025 12:00:00 AM | 9 | 1404/4/7 | 1404/4/8 | 50 | 100 | 0.18867924528301888 | 0.09433962264150944 | 0 | مهندسي پروژه ( آقاي يعقوبي) | 0.18867924528301888 | Edit Details Delete |
| 3.8 | پايان فاز مهندسي | 0.0d | 0.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/06/29 | 6/29/2025 12:00:00 AM | 4,5,7,9,10 | 1404/4/8 | 1404/4/8 | 0 | 100 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 4 | فاز تامين و قالب سازي | 61.0d | 0.0d | 2025/06/07 | 6/7/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 1404/3/17 | 1404/6/3 | 0 | 32 | 15.094339622641511 | 4.905660377358491 | 0 | 47.169811320754725 | Edit Details Delete | ||
| 4.1 | نمونه مقدماتي اگزوزبا منبع ،لوله و هنگر | 61.0d | 0.0d | 2025/06/07 | 6/7/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 1404/3/17 | 1404/6/3 | 0 | 41 | 4.718867924528302 | 3.9622641509433967 | 0 | 11.509433962264152 | Edit Details Delete | ||
| 4.1.1 | انتخاب پيمانكار | 5.0d | 5.0d | 2025/06/07 | 6/7/2025 12:00:00 AM | 2025/06/11 | 6/11/2025 12:00:00 AM | 5 | 1404/3/17 | 1404/3/21 | 100 | 100 | 0.9433962264150944 | 0.9433962264150944 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.1.2 | مذاکره با پیمانکار جهت بررسي و ساخت اگزوز | 16.0d | 16.0d | 2025/06/12 | 6/12/2025 12:00:00 AM | 2025/07/03 | 7/3/2025 12:00:00 AM | 14 | 1404/3/22 | 1404/4/12 | 100 | 100 | 3.018867924528302 | 3.018867924528302 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 3.018867924528302 | Edit Details Delete |
| 4.1.3 | توليد 5 ست بعنوان نمونه اوليه | 35.0d | 35.0d | 2025/07/06 | 7/6/2025 12:00:00 AM | 2025/08/19 | 8/19/2025 12:00:00 AM | 15 | 1404/4/15 | 1404/5/28 | 0 | 11 | 0.7264150943396226 | 0 | 0 | تامين كننده ( ايران اگزوز ) | 6.60377358490566 | Edit Details Delete |
| 4.1.4 | ارسال نمونه هاي اوليه به كارخانه | 5.0d | 5.0d | 2025/08/19 | 8/19/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 16 | 1404/5/28 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( ايران اگزوز ) | 0.9433962264150944 | Edit Details Delete |
| 4.2 | GPF | 18.0d | 0.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/22 | 7/22/2025 12:00:00 AM | 1404/4/8 | 1404/4/31 | 0 | 62 | 3.041509433962264 | 0 | 0 | 4.90566037735849 | Edit Details Delete | ||
| 4.2.1 | X5 توليدقطعات مشابه كاتاباكس(عايق حرارت گير ، شيپوري و براكت ) | 15.0d | 15.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/19 | 7/19/2025 12:00:00 AM | 10 | 1404/4/8 | 1404/4/28 | 0 | 53 | 1.5 | 0 | 0 | تامين كننده كاراحديد نامي | 2.8301886792452833 | Edit Details Delete |
| 4.2.2 | سفارشگذاري و توليد پوسته | 1.0d | 1.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/06/30 | 6/30/2025 12:00:00 AM | 10 | 1404/4/8 | 1404/4/9 | 0 | 100 | 0.18867924528301888 | 0 | 0 | آريا پاك مبدل | 0.18867924528301888 | Edit Details Delete |
| 4.2.3 | تامين مهره و پيچ جوشي براكت | 7.0d | 7.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/08 | 7/8/2025 12:00:00 AM | 10 | 1404/4/8 | 1404/4/17 | 0 | 100 | 1.3207547169811322 | 0 | 0 | سازنده مشخص نشده | 1.3207547169811322 | Edit Details Delete |
| 4.2.4 | ارسال قطعات توليدي به بم | 3.0d | 3.0d | 2025/07/20 | 7/20/2025 12:00:00 AM | 2025/07/22 | 7/22/2025 12:00:00 AM | 19,21,20 | 1404/4/29 | 1404/4/31 | 0 | 0 | 0 | 0 | 0 | تامين كننده كاراحديد نامي | 0.5660377358490566 | Edit Details Delete |
| 4.3 | سر اگزوز | 44.0d | 0.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 1404/4/8 | 1404/6/3 | 0 | 18 | 1.4943396226415095 | 0 | 0 | 8.30188679245283 | Edit Details Delete | ||
| 4.3.1 | انتخاب پيمانكار ساخت قالب | 5.0d | 5.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/06 | 7/6/2025 12:00:00 AM | 10,6 | 1404/4/8 | 1404/4/15 | 0 | 100 | 0.9433962264150944 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.3.2 | عقد قرارداد و پيش پرداخت | 5.0d | 5.0d | 2025/07/07 | 7/7/2025 12:00:00 AM | 2025/07/13 | 7/13/2025 12:00:00 AM | 24 | 1404/4/16 | 1404/4/22 | 0 | 60 | 0.5660377358490566 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.3.3 | ساخت قالب ها | 30.0d | 30.0d | 2025/07/13 | 7/13/2025 12:00:00 AM | 2025/08/20 | 8/20/2025 12:00:00 AM | 25 | 1404/4/22 | 1404/5/29 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( افرا كوشا فدك) | 5.660377358490567 | Edit Details Delete |
| 4.3.4 | توليد نمونه | 2.0d | 2.0d | 2025/08/20 | 8/20/2025 12:00:00 AM | 2025/08/23 | 8/23/2025 12:00:00 AM | 26 | 1404/5/29 | 1404/6/1 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( افرا كوشا فدك) | 0.37735849056603776 | Edit Details Delete |
| 4.3.5 | تائيديه قالب و نمونه | 2.0d | 2.0d | 2025/08/24 | 8/24/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 27 | 1404/6/2 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | مسئول پروژه ( آقاي رضائي فرد) | 0.37735849056603776 | Edit Details Delete |
| 4.4 | Pipe قالبسازي براكت | 44.0d | 0.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 1404/4/8 | 1404/6/3 | 0 | 18 | 1.4943396226415095 | 0 | 0 | 8.30188679245283 | Edit Details Delete | ||
| 4.4.1 | انتخاب پيمانكار ساخت قالب | 5.0d | 5.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/06 | 7/6/2025 12:00:00 AM | 10,6 | 1404/4/8 | 1404/4/15 | 0 | 100 | 0.9433962264150944 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.4.2 | عقد قرارداد و پيش پرداخت | 2.0d | 2.0d | 2025/07/07 | 7/7/2025 12:00:00 AM | 2025/07/08 | 7/8/2025 12:00:00 AM | 30 | 1404/4/16 | 1404/4/17 | 0 | 100 | 0.37735849056603776 | 0 | 0 | سازنده قالب نهائي نشده | 0.37735849056603776 | Edit Details Delete |
| 4.4.3 | ساخت قالب ها | 34.0d | 34.0d | 2025/07/09 | 7/9/2025 12:00:00 AM | 2025/08/21 | 8/21/2025 12:00:00 AM | 31 | 1404/4/18 | 1404/5/30 | 0 | 3 | 0.19245283018867926 | 0 | 0 | سازنده قالب نهائي نشده | 6.415094339622642 | Edit Details Delete |
| 4.4.4 | توليد نمونه | 2.0d | 2.0d | 2025/08/23 | 8/23/2025 12:00:00 AM | 2025/08/24 | 8/24/2025 12:00:00 AM | 32 | 1404/6/1 | 1404/6/2 | 0 | 0 | 0 | 0 | 0 | سازنده قالب نهائي نشده | 0.37735849056603776 | Edit Details Delete |
| 4.4.5 | تائيديه قالب و نمونه | 1.0d | 1.0d | 2025/08/25 | 8/25/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 33 | 1404/6/3 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | سازنده قالب نهائي نشده | 0.18867924528301888 | Edit Details Delete |
| 4.5 | مهره سنسور فشار و دما ( مشترك X5-J7-SR6) | 30.0d | 0.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/08/06 | 8/6/2025 12:00:00 AM | 1404/4/8 | 1404/5/15 | 0 | 27 | 1.5283018867924532 | 0 | 0 | 5.660377358490567 | Edit Details Delete | ||
| 4.5.1 | انتخاب تراشكار | 7.0d | 7.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/08 | 7/8/2025 12:00:00 AM | 10 | 1404/4/8 | 1404/4/17 | 0 | 100 | 1.3207547169811322 | 0 | 0 | ماشين كار مشخص نشده است | 1.3207547169811322 | Edit Details Delete |
| 4.5.2 | عقد قرارداد و پيش پرداخت | 2.0d | 2.0d | 2025/07/09 | 7/9/2025 12:00:00 AM | 2025/07/12 | 7/12/2025 12:00:00 AM | 36 | 1404/4/18 | 1404/4/21 | 0 | 50 | 0.18867924528301888 | 0 | 0 | ماشين كار مشخص نشده است | 0.37735849056603776 | Edit Details Delete |
| 4.5.3 | توليد نمونه | 20.0d | 20.0d | 2025/07/12 | 7/12/2025 12:00:00 AM | 2025/08/05 | 8/5/2025 12:00:00 AM | 37 | 1404/4/21 | 1404/5/14 | 0 | 0 | 0 | 0 | 0 | ماشين كار مشخص نشده است | 3.7735849056603774 | Edit Details Delete |
| 4.5.4 | تائيديه نمونه | 1.0d | 1.0d | 2025/08/06 | 8/6/2025 12:00:00 AM | 2025/08/06 | 8/6/2025 12:00:00 AM | 38 | 1404/5/15 | 1404/5/15 | 0 | 0 | 0 | 0 | 0 | ماشين كار مشخص نشده است | 0.18867924528301888 | Edit Details Delete |
| 4.6 | منجيد(مشابه ) | 10.0d | 0.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/13 | 7/13/2025 12:00:00 AM | 1404/4/8 | 1404/4/22 | 0 | 80 | 1.509433962264151 | 0.9433962264150944 | 0 | 1.8867924528301887 | Edit Details Delete | ||
| 4.6.1 | تامين منجيد دو سوراخ | 10.0d | 10.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/07/13 | 7/13/2025 12:00:00 AM | 10 | 1404/4/8 | 1404/4/22 | 50 | 80 | 1.509433962264151 | 0.9433962264150944 | 0 | آذين پليمر/ بازرگاني(آقاي صفائي) | 1.8867924528301887 | Edit Details Delete |
| 4.7 | مت و منوليت | 35.0d | 0.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/08/13 | 8/13/2025 12:00:00 AM | 1404/4/8 | 1404/5/22 | 0 | 23 | 1.5188679245283019 | 0 | 0 | 6.60377358490566 | Edit Details Delete | ||
| 4.7.1 | سفارش گذاري براي پك ckd مت منوليت | 35.0d | 35.0d | 2025/06/29 | 6/29/2025 12:00:00 AM | 2025/08/13 | 8/13/2025 12:00:00 AM | 10 | 1404/4/8 | 1404/5/22 | 0 | 23 | 1.5188679245283019 | 0 | 0 | بازرگاني خارجي ( آقاي محمودي) | 6.60377358490566 | Edit Details Delete |
| 4.8 | پايان تامين و قالب سازي | 0.0d | 0.0d | 2025/08/25 | 8/25/2025 12:00:00 AM | 2025/08/25 | 8/25/2025 12:00:00 AM | 22,17,28,34,39,41,43 | 1404/6/3 | 1404/6/3 | 0 | 0 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 5 | فاز نمونه اوليه وساخت فيكسچر | 98.0d | 0.0d | 2025/08/26 | 8/26/2025 12:00:00 AM | 2025/12/31 | 12/31/2025 12:00:00 AM | 1404/6/4 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | 32.83018867924529 | Edit Details Delete | ||
| 5.1 | توليد 5 عدد مجموعه اگزوز اوليه | 2.0d | 2.0d | 2025/08/26 | 8/26/2025 12:00:00 AM | 2025/08/27 | 8/27/2025 12:00:00 AM | 17,44 | 1404/6/4 | 1404/6/5 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول ( آقاي غضنفري) | 0.37735849056603776 | Edit Details Delete |
| 5.2 | تحويل به مهندسي محصول كرمان موتور جهت بررسي | 3.0d | 3.0d | 2025/08/28 | 8/28/2025 12:00:00 AM | 2025/09/02 | 9/2/2025 12:00:00 AM | 46 | 1404/6/6 | 1404/6/11 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول ( آقاي غضنفري)/مهندسي محصول كرمان موتور ( آقاي تيرگر) | 0.5660377358490566 | Edit Details Delete |
| 5.3 | ثبت كارتابل نمونه اوليه | 2.0d | 2.0d | 2025/09/02 | 9/2/2025 12:00:00 AM | 2025/09/04 | 9/4/2025 12:00:00 AM | 47 | 1404/6/11 | 1404/6/13 | 0 | 0 | 0 | 0 | 0 | كادك ( خانم معافي) | 0.37735849056603776 | Edit Details Delete |
| 5.4 | اخذ تاييديه نمونه اوليه | 10.0d | 0.0d | 2025/09/06 | 9/6/2025 12:00:00 AM | 2025/09/18 | 9/18/2025 12:00:00 AM | 1404/6/15 | 1404/6/27 | 0 | 0 | 0 | 0 | 0 | 1.8867924528301887 | Edit Details Delete | ||
| 5.4.1 | انجام تست هاي مونتاژ پذيري در بم | 5.0d | 5.0d | 2025/09/06 | 9/6/2025 12:00:00 AM | 2025/09/13 | 9/13/2025 12:00:00 AM | 48 | 1404/6/15 | 1404/6/22 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 0.9433962264150944 | Edit Details Delete |
| 5.4.2 | ارسال گزارش | 2.0d | 2.0d | 2025/09/13 | 9/13/2025 12:00:00 AM | 2025/09/15 | 9/15/2025 12:00:00 AM | 50 | 1404/6/22 | 1404/6/24 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 0.37735849056603776 | Edit Details Delete |
| 5.4.3 | اخذ تائيديه | 3.0d | 3.0d | 2025/09/15 | 9/15/2025 12:00:00 AM | 2025/09/18 | 9/18/2025 12:00:00 AM | 51 | 1404/6/24 | 1404/6/27 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.5660377358490566 | Edit Details Delete |
| 5.5 | تهيه نهايي BOM | 2.0d | 2.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2025/09/21 | 9/21/2025 12:00:00 AM | 52 | 1404/6/29 | 1404/6/30 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول( خانم فرامرز پور) | 0.37735849056603776 | Edit Details Delete |
| 5.6 | آدیت تضمین کیفیت | 1.0d | 1.0d | 2025/09/22 | 9/22/2025 12:00:00 AM | 2025/09/22 | 9/22/2025 12:00:00 AM | 53,52 | 1404/6/31 | 1404/6/31 | 0 | 0 | 0 | 0 | 0 | تضمين كيفيت ( آقاي جلال الديني) | 0.18867924528301888 | Edit Details Delete |
| 5.7 | تست آلايندگي | 50.0d | 0.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2025/11/22 | 11/22/2025 12:00:00 AM | 1404/6/29 | 1404/9/1 | 0 | 0 | 0 | 0 | 0 | 9.433962264150944 | Edit Details Delete | ||
| 5.7.1 | ارسال نمونه به تهران جهت ارسال به كرمان موتور براي انجام تست | 3.0d | 3.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2025/09/22 | 9/22/2025 12:00:00 AM | 52 | 1404/6/29 | 1404/6/31 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 0.5660377358490566 | Edit Details Delete |
| 5.7.2 | تست آلايندگي و تست توان سر چرخ نمونه مطالعاتی | 45.0d | 45.0d | 2025/09/23 | 9/23/2025 12:00:00 AM | 2025/11/18 | 11/18/2025 12:00:00 AM | 56 | 1404/7/1 | 1404/8/27 | 0 | 0 | 0 | 0 | 0 | مهندسي محصول كرمان موتور | 8.49056603773585 | Edit Details Delete |
| 5.7.3 | ارسال نتايج به آرمان موتور جهت ثبت در آرشيو فني | 2.0d | 2.0d | 2025/11/19 | 11/19/2025 12:00:00 AM | 2025/11/22 | 11/22/2025 12:00:00 AM | 57 | 1404/8/28 | 1404/9/1 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.37735849056603776 | Edit Details Delete |
| 5.8 | فيكسچرهاي توليدي وكنترلي | 81.0d | 0.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2025/12/31 | 12/31/2025 12:00:00 AM | 1404/6/29 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | 19.62264150943396 | Edit Details Delete | ||
| 5.8.1 | طراحي فيكسچر | 29.0d | 0.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2025/10/26 | 10/26/2025 12:00:00 AM | 1404/6/29 | 1404/8/4 | 0 | 0 | 0 | 0 | 0 | 5.471698113207547 | Edit Details Delete | ||
| 5.8.1.1 | اسكن نمونه تائيد شده و مدلسازي | 14.0d | 14.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2025/10/06 | 10/6/2025 12:00:00 AM | 52 | 1404/6/29 | 1404/7/14 | 0 | 0 | 0 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 2.6415094339622645 | Edit Details Delete |
| 5.8.1.2 | طراحي فيكسچر توليدي و كنترلي | 10.0d | 10.0d | 2025/10/07 | 10/7/2025 12:00:00 AM | 2025/10/19 | 10/19/2025 12:00:00 AM | 61 | 1404/7/15 | 1404/7/27 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي يوسفيان) | 1.8867924528301887 | Edit Details Delete |
| 5.8.1.3 | اخذ تائيديه براي فيكسچرهاي كنترلي مجموعه نهايي از كادك | 5.0d | 5.0d | 2025/10/20 | 10/20/2025 12:00:00 AM | 2025/10/26 | 10/26/2025 12:00:00 AM | 62 | 1404/7/28 | 1404/8/4 | 0 | 0 | 0 | 0 | 0 | الزامات كادك ( آقاي صالحي) | 0.9433962264150944 | Edit Details Delete |
| 5.8.2 | ساخت فيكسچرتوليدي | 23.0d | 0.0d | 2025/10/26 | 10/26/2025 12:00:00 AM | 2025/11/25 | 11/25/2025 12:00:00 AM | 1404/8/4 | 1404/9/4 | 0 | 0 | 0 | 0 | 0 | 4.339622641509434 | Edit Details Delete | ||
| 5.8.2.1 | ليزر برش قطعات فيكسچر توليدي | 15.0d | 0.0d | 2025/10/26 | 10/26/2025 12:00:00 AM | 2025/11/13 | 11/13/2025 12:00:00 AM | 63 | 1404/8/4 | 1404/8/22 | 0 | 0 | 0 | 0 | 0 | سازنده مشخص نشده | 2.8301886792452833 | Edit Details Delete |
| 5.8.2.2 | ارسال فيكسچر به بم | 3.0d | 3.0d | 2025/11/15 | 11/15/2025 12:00:00 AM | 2025/11/17 | 11/17/2025 12:00:00 AM | 65 | 1404/8/24 | 1404/8/26 | 0 | 0 | 0 | 0 | 0 | بازرگاني ( آقاي مرادي),مهندسي پروژه ( آقاي يوسفيان) | 0.5660377358490566 | Edit Details Delete |
| 5.8.2.3 | مونتاژ فيكسچر هاي توليدي در كارخانه | 5.0d | 5.0d | 2025/11/18 | 11/18/2025 12:00:00 AM | 2025/11/25 | 11/25/2025 12:00:00 AM | 66 | 1404/8/27 | 1404/9/4 | 0 | 0 | 0 | 0 | 0 | مهندسي ابزار(آقاي ترك پور) | 0.9433962264150944 | Edit Details Delete |
| 5.8.3 | ساخت فيكسچركنترلي | 50.0d | 0.0d | 2025/10/26 | 10/26/2025 12:00:00 AM | 2025/12/29 | 12/29/2025 12:00:00 AM | 1404/8/4 | 1404/10/8 | 0 | 0 | 0 | 0 | 0 | 9.433962264150944 | Edit Details Delete | ||
| 5.8.3.1 | ساخت فيكسچرهاي كنترلي | 45.0d | 45.0d | 2025/10/26 | 10/26/2025 12:00:00 AM | 2025/12/23 | 12/23/2025 12:00:00 AM | 62,63 | 1404/8/4 | 1404/10/2 | 0 | 0 | 0 | 0 | 0 | سازنده مشخص نشده | 8.49056603773585 | Edit Details Delete |
| 5.8.3.2 | گزارش گيري ابعادي/ cmm | 2.0d | 2.0d | 2025/12/23 | 12/23/2025 12:00:00 AM | 2025/12/25 | 12/25/2025 12:00:00 AM | 69 | 1404/10/2 | 1404/10/4 | 0 | 0 | 0 | 0 | 0 | سازنده مشخص نشده | 0.37735849056603776 | Edit Details Delete |
| 5.8.3.3 | ارسال فيكسچر به بم | 3.0d | 3.0d | 2025/12/27 | 12/27/2025 12:00:00 AM | 2025/12/29 | 12/29/2025 12:00:00 AM | 70 | 1404/10/6 | 1404/10/8 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي يوسفيان),بازرگاني ( آقاي مرادي) | 0.5660377358490566 | Edit Details Delete |
| 5.8.4 | صورتجلسه تائيد و تحويل فيكسچرها به واحد توليد | 2.0d | 2.0d | 2025/12/30 | 12/30/2025 12:00:00 AM | 2025/12/31 | 12/31/2025 12:00:00 AM | 67,71 | 1404/10/9 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي يوسفيان),مهندسي ابزار(آقاي ترك پور) | 0.37735849056603776 | Edit Details Delete |
| 5.9 | پايان فاز | 0.0d | 0.0d | 2025/12/31 | 12/31/2025 12:00:00 AM | 2025/12/31 | 12/31/2025 12:00:00 AM | 52,58,67,63,71,72 | 1404/10/10 | 1404/10/10 | 0 | 0 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 6 | فاز يك روز خط | 87.0d | 0.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2026/01/08 | 1/8/2026 12:00:00 AM | 1404/6/29 | 1404/10/18 | 0 | 0 | 0 | 0 | 0 | 12.830188679245284 | Edit Details Delete | ||
| 6.1 | سفارش گذاري 100 ست | 5.0d | 5.0d | 2025/09/20 | 9/20/2025 12:00:00 AM | 2025/09/24 | 9/24/2025 12:00:00 AM | 49,52 | 1404/6/29 | 1404/7/2 | 0 | 0 | 0 | 0 | 0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 6.2 | توليد و ارسال قطعات يك روز خط به كارخانه | 10.0d | 10.0d | 2025/09/25 | 9/25/2025 12:00:00 AM | 2025/10/07 | 10/7/2025 12:00:00 AM | 75 | 1404/7/3 | 1404/7/15 | 0 | 0 | 0 | 0 | 0 | تامين كننده ( ايران اگزوز ) | 1.8867924528301887 | Edit Details Delete |
| 6.3 | آديت فرآيند واحد تضمين كيفيت | 1.0d | 1.0d | 2025/10/08 | 10/8/2025 12:00:00 AM | 2025/10/08 | 10/8/2025 12:00:00 AM | 76 | 1404/7/16 | 1404/7/16 | 0 | 0 | 0 | 0 | 0 | تضمين كيفيت ( آقاي جلال الديني) | 0.18867924528301888 | Edit Details Delete |
| 6.4 | توليد يك روز خط اگزوز در آرمان موتور | 4.0d | 4.0d | 2025/11/25 | 11/25/2025 12:00:00 AM | 2025/11/30 | 11/30/2025 12:00:00 AM | 77,76,67 | 1404/9/4 | 1404/9/9 | 0 | 0 | 0 | 0 | 0 | مهندسي توليد /مهندسي پروژه | 0.7547169811320755 | Edit Details Delete |
| 6.5 | ثبت كارتابل يك روز خط و ارسال قطعات به خط توليد كرمان موتور | 3.0d | 3.0d | 2025/12/01 | 12/1/2025 12:00:00 AM | 2025/12/03 | 12/3/2025 12:00:00 AM | 78 | 1404/9/10 | 1404/9/12 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.5660377358490566 | Edit Details Delete |
| 6.6 | مونتاژ يك روز خط-بسته به برنامه توليد | 3.0d | 3.0d | 2025/12/04 | 12/4/2025 12:00:00 AM | 2025/12/08 | 12/8/2025 12:00:00 AM | 79 | 1404/9/13 | 1404/9/17 | 0 | 0 | 0 | 0 | 0 | مهندسي توليد /مهندسي پروژه | 0.5660377358490566 | Edit Details Delete |
| 6.7 | ارزيابي يك روز خط | 4.0d | 4.0d | 2026/01/01 | 1/1/2026 12:00:00 AM | 2026/01/06 | 1/6/2026 12:00:00 AM | 80,73 | 1404/10/11 | 1404/10/16 | 0 | 0 | 0 | 0 | 0 | كادك ( آقاي عبدي) | 0.7547169811320755 | Edit Details Delete |
| 6.8 | تاييديه يك روز خط | 2.0d | 2.0d | 2026/01/06 | 1/6/2026 12:00:00 AM | 2026/01/08 | 1/8/2026 12:00:00 AM | 81 | 1404/10/16 | 1404/10/18 | 0 | 0 | 0 | 0 | 0 | كادك ( آقاي عبدي) | 0.37735849056603776 | Edit Details Delete |
| 6.9 | انجام تست هاي ذكر شده در تست پلن، تهيه تست ريپورت | 36.0d | 0.0d | 2025/11/22 | 11/22/2025 12:00:00 AM | 2026/01/07 | 1/7/2026 12:00:00 AM | 1404/9/1 | 1404/10/17 | 0 | 0 | 0 | 0 | 0 | 6.7924528301886795 | Edit Details Delete | ||
| 6.9.1 | دريافت پيش فاكتور از آزمايشگاه | 2.0d | 2.0d | 2025/11/22 | 11/22/2025 12:00:00 AM | 2025/11/25 | 11/25/2025 12:00:00 AM | 58 | 1404/9/1 | 1404/9/4 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.37735849056603776 | Edit Details Delete |
| 6.9.2 | پرداخت مبلغ انجام تست | 2.0d | 2.0d | 2025/11/25 | 11/25/2025 12:00:00 AM | 2025/11/27 | 11/27/2025 12:00:00 AM | 84 | 1404/9/4 | 1404/9/6 | 0 | 0 | 0 | 0 | 0 | خزانه ( آقاي محمودي) | 0.37735849056603776 | Edit Details Delete |
| 6.9.3 | ارسال قطعات به ازمايشگاه | 2.0d | 2.0d | 2025/11/29 | 11/29/2025 12:00:00 AM | 2025/11/30 | 11/30/2025 12:00:00 AM | 85 | 1404/9/8 | 1404/9/9 | 0 | 0 | 0 | 0 | 0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.37735849056603776 | Edit Details Delete |
| 6.9.4 | انجام آزمون و تهيه تست ريپورت | 30.0d | 30.0d | 2025/12/01 | 12/1/2025 12:00:00 AM | 2026/01/07 | 1/7/2026 12:00:00 AM | 86 | 1404/9/10 | 1404/10/17 | 0 | 0 | 0 | 0 | 0 | آزمايشگاه مشخص نيست | 5.660377358490567 | Edit Details Delete |
| 7 | اتمام پروژه- سفارشگذاري جهت توليد انبوه | 0.0d | 0.0d | 2026/01/08 | 1/8/2026 12:00:00 AM | 2026/01/08 | 1/8/2026 12:00:00 AM | 82,83 | 1404/10/18 | 1404/10/18 | 0 | 0 | 0 | 0 | 0 | 0 | Edit Details Delete | |
| 0 | Exhaust-SR6 | 0.398958 | 0.398958 | 2025/05/01 | 2025-05-01 08:00 | 2026/01/08 | 2026-01-08 12:00 | 1404/2/11 | 1404/10/18 | 0 | 22.0 | 0 | 42.9971 | 0.0 | 99.99999999999997 | Edit Details Delete | ||
| 1 | امكان سنجي و توجيه اقتصادي پروژه | 0 | 0 | 2025/05/01 | 2025-05-01 08:00 | 2025/05/01 | 2025-05-01 08:00 | 1404/2/11 | 1404/2/11 | 0 | 100.0 | 0 | 0 | 0.0 | مسئول پروژه ( آقاي رضائي فرد)/كنترل پروژه | 0.0 | Edit Details Delete | |
| 2 | شروع پروژه | 0 | 0 | 2025/05/01 | 2025-05-01 08:00 | 2025/05/01 | 2025-05-01 08:00 | 1 | 1404/2/11 | 1404/2/11 | 0 | 100.0 | 0 | 0 | 0.0 | 0.0 | Edit Details Delete | |
| 3 | فاز مهندسي | 0.090625 | 0.090625 | 2025/05/01 | 2025-05-01 08:00 | 2025/06/29 | 2025-06-29 12:00 | 1 | 1404/2/11 | 1404/4/8 | 0 | 100.0 | 0 | 43.5 | 0.0 | 7.169811320754718 | Edit Details Delete | |
| 3.1 | دريافت اطلاعات فني از مشتري (نقشه، شناسنامه فني ، تست پلن و ...) | 0.0145833 | 0.0145833 | 2025/05/01 | 2025-05-01 08:00 | 2025/05/10 | 2025-05-10 17:00 | 1 | 1404/2/11 | 1404/2/20 | 50 | 100.0 | 0 | 7 | 0.0 | مهندسي پروژه ( آقاي ابراهيم ) | 1.3207547169811322 | Edit Details Delete |
| 3.2 | دريافت نمونه اگزوز وارداتي ( مجموعه كامل) | 0.00416667 | 0.00416667 | 2025/06/03 | 2025-06-03 08:00 | 2025/06/04 | 2025-06-04 17:00 | 1 | 1404/3/13 | 1404/3/14 | 100 | 100.0 | 0 | 2 | 0.0 | مهندسي پروژه ( آقاي يعقوبي) | 0.37735849056603776 | Edit Details Delete |
| 3.3 | دريافت نمونه اگزوز وارداتي (منفصله ) | 0.0145833 | 0.0145833 | 2025/05/01 | 2025-05-01 08:00 | 2025/05/10 | 2025-05-10 17:00 | 1 | 1404/2/11 | 1404/2/20 | 100 | 100.0 | 0 | 7 | 0.0 | مهندسي پروژه ( آقاي يعقوبي) | 1.3207547169811322 | Edit Details Delete |
| 3.4 | spl /Bomتهيه اوليه | 0.0104167 | 0.0104167 | 2025/06/07 | 2025-06-07 08:00 | 2025/06/11 | 2025-06-11 17:00 | 5,4 | 1404/3/17 | 1404/3/21 | 50 | 100.0 | 0 | 5 | 0.0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.9433962264150944 | Edit Details Delete |
| 3.5 | اسكن اگزوز دريافتي | 0.0291667 | 0.0291667 | 2025/06/07 | 2025-06-07 08:00 | 2025/06/24 | 2025-06-24 17:00 | 5 | 1404/3/17 | 1404/4/3 | 50 | 100.0 | 0 | 14 | 0.0 | بازرگاني ( آقاي مرادي) | 2.6415094339622645 | Edit Details Delete |
| 3.6 | بررسي نمونه دريافتي با نقشه هاو اعلام مغايرت ها /bom | 0.00416667 | 0.00416667 | 2025/06/25 | 2025-06-25 08:00 | 2025/06/28 | 2025-06-28 12:00 | 4,8 | 1404/4/4 | 1404/4/7 | 20 | 100.0 | 0 | 2 | 0.0 | مسئول پروژه ( آقاي رضائي فرد) | 0.37735849056603776 | Edit Details Delete |
| 3.7 | تهيه و ارسال نقشه هاي اگزوز به واحد بازرگاني | 0.00208333 | 0.00208333 | 2025/06/28 | 2025-06-28 13:00 | 2025/06/29 | 2025-06-29 12:00 | 9 | 1404/4/7 | 1404/4/8 | 50 | 100.0 | 0 | 1 | 0.0 | مهندسي پروژه ( آقاي يعقوبي) | 0.18867924528301888 | Edit Details Delete |
| 3.8 | پايان فاز مهندسي | 0 | 0 | 2025/06/29 | 2025-06-29 12:00 | 2025/06/29 | 2025-06-29 12:00 | 4,5,7,9,10 | 1404/4/8 | 1404/4/8 | 0 | 100.0 | 0 | 0 | 0.0 | 0.0 | Edit Details Delete | |
| 4 | فاز تامين و قالب سازي | 0.127083 | 0.127083 | 2025/06/07 | 2025-06-07 08:00 | 2025/08/25 | 2025-08-25 17:00 | 1404/3/17 | 1404/6/3 | 0 | 32.0 | 0 | 19.764 | 0.0 | 47.169811320754725 | Edit Details Delete | ||
| 4.1 | نمونه مقدماتي اگزوزبا منبع ،لوله و هنگر | 0.127083 | 0.127083 | 2025/06/07 | 2025-06-07 08:00 | 2025/08/25 | 2025-08-25 17:00 | 1404/3/17 | 1404/6/3 | 0 | 41.0 | 0 | 25 | 0.0 | 11.509433962264152 | Edit Details Delete | ||
| 4.1.1 | انتخاب پيمانكار | 0.0104167 | 0.0104167 | 2025/06/07 | 2025-06-07 08:00 | 2025/06/11 | 2025-06-11 17:00 | 5 | 1404/3/17 | 1404/3/21 | 100 | 100.0 | 0 | 5 | 0.0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.1.2 | مذاکره با پیمانکار جهت بررسي و ساخت اگزوز | 0.0333333 | 0.0333333 | 2025/06/12 | 2025-06-12 08:00 | 2025/07/03 | 2025-07-03 17:00 | 14 | 1404/3/22 | 1404/4/12 | 100 | 100.0 | 0 | 16 | 0.0 | بازرگاني ( آقايان صفائي / نظري ) | 3.018867924528302 | Edit Details Delete |
| 4.1.3 | توليد 5 ست بعنوان نمونه اوليه | 0.0729167 | 0.0729167 | 2025/07/06 | 2025-07-06 08:00 | 2025/08/19 | 2025-08-19 12:00 | 15 | 1404/4/15 | 1404/5/28 | 0 | 11.0 | 0 | 4 | 0.0 | تامين كننده ( ايران اگزوز ) | 6.60377358490566 | Edit Details Delete |
| 4.1.4 | ارسال نمونه هاي اوليه به كارخانه | 0.0104167 | 0.0104167 | 2025/08/19 | 2025-08-19 13:00 | 2025/08/25 | 2025-08-25 17:00 | 16 | 1404/5/28 | 1404/6/3 | 0 | 0.0 | 0 | 0 | 0.0 | تامين كننده ( ايران اگزوز ) | 0.9433962264150944 | Edit Details Delete |
| 4.2 | GPF | 0.0375 | 0.0375 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/22 | 2025-07-22 17:00 | 1404/4/8 | 1404/4/31 | 0 | 62.0 | 0 | 11.0769 | 0.0 | 4.90566037735849 | Edit Details Delete | ||
| 4.2.1 | X5 توليدقطعات مشابه كاتاباكس(عايق حرارت گير ، شيپوري و براكت ) | 0.03125 | 0.03125 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/19 | 2025-07-19 17:00 | 10 | 1404/4/8 | 1404/4/28 | 0 | 53.0 | 0 | 8 | 0.0 | تامين كننده كاراحديد نامي | 2.8301886792452833 | Edit Details Delete |
| 4.2.2 | سفارشگذاري و توليد پوسته | 0.00208333 | 0.00208333 | 2025/06/29 | 2025-06-29 13:00 | 2025/06/30 | 2025-06-30 12:00 | 10 | 1404/4/8 | 1404/4/9 | 0 | 100.0 | 0 | 1 | 0.0 | آريا پاك مبدل | 0.18867924528301888 | Edit Details Delete |
| 4.2.3 | تامين مهره و پيچ جوشي براكت | 0.0145833 | 0.0145833 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/08 | 2025-07-08 17:00 | 10 | 1404/4/8 | 1404/4/17 | 0 | 100.0 | 0 | 7 | 0.0 | سازنده مشخص نشده | 1.3207547169811322 | Edit Details Delete |
| 4.2.4 | ارسال قطعات توليدي به بم | 0.00625 | 0.00625 | 2025/07/20 | 2025-07-20 08:00 | 2025/07/22 | 2025-07-22 17:00 | 19,21,20 | 1404/4/29 | 1404/4/31 | 0 | 0.0 | 0 | 0 | 0.0 | تامين كننده كاراحديد نامي | 0.5660377358490566 | Edit Details Delete |
| 4.3 | سر اگزوز | 0.0916667 | 0.0916667 | 2025/06/29 | 2025-06-29 13:00 | 2025/08/25 | 2025-08-25 17:00 | 1404/4/8 | 1404/6/3 | 0 | 18.0 | 0 | 8 | 0.0 | 8.30188679245283 | Edit Details Delete | ||
| 4.3.1 | انتخاب پيمانكار ساخت قالب | 0.0104167 | 0.0104167 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/06 | 2025-07-06 17:00 | 10,6 | 1404/4/8 | 1404/4/15 | 0 | 100.0 | 0 | 5 | 0.0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.3.2 | عقد قرارداد و پيش پرداخت | 0.0104167 | 0.0104167 | 2025/07/07 | 2025-07-07 08:00 | 2025/07/13 | 2025-07-13 12:00 | 24 | 1404/4/16 | 1404/4/22 | 0 | 60.0 | 0 | 3 | 0.0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.3.3 | ساخت قالب ها | 0.0625 | 0.0625 | 2025/07/13 | 2025-07-13 13:00 | 2025/08/20 | 2025-08-20 12:00 | 25 | 1404/4/22 | 1404/5/29 | 0 | 0.0 | 0 | 0 | 0.0 | تامين كننده ( افرا كوشا فدك) | 5.660377358490567 | Edit Details Delete |
| 4.3.4 | توليد نمونه | 0.00416667 | 0.00416667 | 2025/08/20 | 2025-08-20 13:00 | 2025/08/23 | 2025-08-23 17:00 | 26 | 1404/5/29 | 1404/6/1 | 0 | 0.0 | 0 | 0 | 0.0 | تامين كننده ( افرا كوشا فدك) | 0.37735849056603776 | Edit Details Delete |
| 4.3.5 | تائيديه قالب و نمونه | 0.00416667 | 0.00416667 | 2025/08/24 | 2025-08-24 08:00 | 2025/08/25 | 2025-08-25 17:00 | 27 | 1404/6/2 | 1404/6/3 | 0 | 0.0 | 0 | 0 | 0.0 | مسئول پروژه ( آقاي رضائي فرد) | 0.37735849056603776 | Edit Details Delete |
| 4.4 | Pipe قالبسازي براكت | 0.0916667 | 0.0916667 | 2025/06/29 | 2025-06-29 13:00 | 2025/08/25 | 2025-08-25 17:00 | 1404/4/8 | 1404/6/3 | 0 | 18.0 | 0 | 8 | 0.0 | 8.30188679245283 | Edit Details Delete | ||
| 4.4.1 | انتخاب پيمانكار ساخت قالب | 0.0104167 | 0.0104167 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/06 | 2025-07-06 17:00 | 10,6 | 1404/4/8 | 1404/4/15 | 0 | 100.0 | 0 | 5 | 0.0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 4.4.2 | عقد قرارداد و پيش پرداخت | 0.00416667 | 0.00416667 | 2025/07/07 | 2025-07-07 08:00 | 2025/07/08 | 2025-07-08 17:00 | 30 | 1404/4/16 | 1404/4/17 | 0 | 100.0 | 0 | 2 | 0.0 | سازنده قالب نهائي نشده | 0.37735849056603776 | Edit Details Delete |
| 4.4.3 | ساخت قالب ها | 0.0708333 | 0.0708333 | 2025/07/09 | 2025-07-09 08:00 | 2025/08/21 | 2025-08-21 12:00 | 31 | 1404/4/18 | 1404/5/30 | 0 | 3.0 | 0 | 1 | 0.0 | سازنده قالب نهائي نشده | 6.415094339622642 | Edit Details Delete |
| 4.4.4 | توليد نمونه | 0.00416667 | 0.00416667 | 2025/08/23 | 2025-08-23 08:00 | 2025/08/24 | 2025-08-24 17:00 | 32 | 1404/6/1 | 1404/6/2 | 0 | 0.0 | 0 | 0 | 0.0 | سازنده قالب نهائي نشده | 0.37735849056603776 | Edit Details Delete |
| 4.4.5 | تائيديه قالب و نمونه | 0.00208333 | 0.00208333 | 2025/08/25 | 2025-08-25 08:00 | 2025/08/25 | 2025-08-25 17:00 | 33 | 1404/6/3 | 1404/6/3 | 0 | 0.0 | 0 | 0 | 0.0 | سازنده قالب نهائي نشده | 0.18867924528301888 | Edit Details Delete |
| 4.5 | مهره سنسور فشار و دما ( مشترك X5-J7-SR6) | 0.0625 | 0.0625 | 2025/06/29 | 2025-06-29 13:00 | 2025/08/06 | 2025-08-06 17:00 | 1404/4/8 | 1404/5/15 | 0 | 27.0 | 0 | 8 | 0.0 | 5.660377358490567 | Edit Details Delete | ||
| 4.5.1 | انتخاب تراشكار | 0.0145833 | 0.0145833 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/08 | 2025-07-08 17:00 | 10 | 1404/4/8 | 1404/4/17 | 0 | 100.0 | 0 | 7 | 0.0 | ماشين كار مشخص نشده است | 1.3207547169811322 | Edit Details Delete |
| 4.5.2 | عقد قرارداد و پيش پرداخت | 0.00416667 | 0.00416667 | 2025/07/09 | 2025-07-09 08:00 | 2025/07/12 | 2025-07-12 12:00 | 36 | 1404/4/18 | 1404/4/21 | 0 | 50.0 | 0 | 1 | 0.0 | ماشين كار مشخص نشده است | 0.37735849056603776 | Edit Details Delete |
| 4.5.3 | توليد نمونه | 0.0416667 | 0.0416667 | 2025/07/12 | 2025-07-12 13:00 | 2025/08/05 | 2025-08-05 17:00 | 37 | 1404/4/21 | 1404/5/14 | 0 | 0.0 | 0 | 0 | 0.0 | ماشين كار مشخص نشده است | 3.7735849056603774 | Edit Details Delete |
| 4.5.4 | تائيديه نمونه | 0.00208333 | 0.00208333 | 2025/08/06 | 2025-08-06 08:00 | 2025/08/06 | 2025-08-06 17:00 | 38 | 1404/5/15 | 1404/5/15 | 0 | 0.0 | 0 | 0 | 0.0 | ماشين كار مشخص نشده است | 0.18867924528301888 | Edit Details Delete |
| 4.6 | منجيد(مشابه ) | 0.0208333 | 0.0208333 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/13 | 2025-07-13 12:00 | 1404/4/8 | 1404/4/22 | 0 | 80.0 | 0 | 8 | 0.0 | 1.8867924528301887 | Edit Details Delete | ||
| 4.6.1 | تامين منجيد دو سوراخ | 0.0208333 | 0.0208333 | 2025/06/29 | 2025-06-29 13:00 | 2025/07/13 | 2025-07-13 12:00 | 10 | 1404/4/8 | 1404/4/22 | 50 | 80.0 | 0 | 8 | 0.0 | آذين پليمر/ بازرگاني(آقاي صفائي) | 1.8867924528301887 | Edit Details Delete |
| 4.7 | مت و منوليت | 0.0729167 | 0.0729167 | 2025/06/29 | 2025-06-29 13:00 | 2025/08/13 | 2025-08-13 12:00 | 1404/4/8 | 1404/5/22 | 0 | 23.0 | 0 | 8 | 0.0 | 6.60377358490566 | Edit Details Delete | ||
| 4.7.1 | سفارش گذاري براي پك ckd مت منوليت | 0.0729167 | 0.0729167 | 2025/06/29 | 2025-06-29 13:00 | 2025/08/13 | 2025-08-13 12:00 | 10 | 1404/4/8 | 1404/5/22 | 0 | 23.0 | 0 | 8 | 0.0 | بازرگاني خارجي ( آقاي محمودي) | 6.60377358490566 | Edit Details Delete |
| 4.8 | پايان تامين و قالب سازي | 0 | 0 | 2025/08/25 | 2025-08-25 17:00 | 2025/08/25 | 2025-08-25 17:00 | 22,17,28,34,39,41,43 | 1404/6/3 | 1404/6/3 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0 | Edit Details Delete | |
| 5 | فاز نمونه اوليه وساخت فيكسچر | 0.204167 | 0.204167 | 2025/08/26 | 2025-08-26 08:00 | 2025/12/31 | 2025-12-31 17:00 | 1404/6/4 | 1404/10/10 | 0 | 0.0 | 0 | 0 | 0.0 | 32.83018867924529 | Edit Details Delete | ||
| 5.1 | توليد 5 عدد مجموعه اگزوز اوليه | 0.00416667 | 0.00416667 | 2025/08/26 | 2025-08-26 08:00 | 2025/08/27 | 2025-08-27 17:00 | 17,44 | 1404/6/4 | 1404/6/5 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي محصول ( آقاي غضنفري) | 0.37735849056603776 | Edit Details Delete |
| 5.2 | تحويل به مهندسي محصول كرمان موتور جهت بررسي | 0.00625 | 0.00625 | 2025/08/28 | 2025-08-28 08:00 | 2025/09/02 | 2025-09-02 12:00 | 46 | 1404/6/6 | 1404/6/11 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي محصول ( آقاي غضنفري)/مهندسي محصول كرمان موتور ( آقاي تيرگر) | 0.5660377358490566 | Edit Details Delete |
| 5.3 | ثبت كارتابل نمونه اوليه | 0.00416667 | 0.00416667 | 2025/09/02 | 2025-09-02 13:00 | 2025/09/04 | 2025-09-04 12:00 | 47 | 1404/6/11 | 1404/6/13 | 0 | 0.0 | 0 | 0 | 0.0 | كادك ( خانم معافي) | 0.37735849056603776 | Edit Details Delete |
| 5.4 | اخذ تاييديه نمونه اوليه | 0.0208333 | 0.0208333 | 2025/09/06 | 2025-09-06 08:00 | 2025/09/18 | 2025-09-18 12:00 | 1404/6/15 | 1404/6/27 | 0 | 0.0 | 0 | 0 | 0.0 | 1.8867924528301887 | Edit Details Delete | ||
| 5.4.1 | انجام تست هاي مونتاژ پذيري در بم | 0.0104167 | 0.0104167 | 2025/09/06 | 2025-09-06 08:00 | 2025/09/13 | 2025-09-13 12:00 | 48 | 1404/6/15 | 1404/6/22 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي محصول كرمان موتور | 0.9433962264150944 | Edit Details Delete |
| 5.4.2 | ارسال گزارش | 0.00416667 | 0.00416667 | 2025/09/13 | 2025-09-13 13:00 | 2025/09/15 | 2025-09-15 12:00 | 50 | 1404/6/22 | 1404/6/24 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي محصول كرمان موتور | 0.37735849056603776 | Edit Details Delete |
| 5.4.3 | اخذ تائيديه | 0.00625 | 0.00625 | 2025/09/15 | 2025-09-15 13:00 | 2025/09/18 | 2025-09-18 12:00 | 51 | 1404/6/24 | 1404/6/27 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.5660377358490566 | Edit Details Delete |
| 5.5 | تهيه نهايي BOM | 0.00416667 | 0.00416667 | 2025/09/20 | 2025-09-20 08:00 | 2025/09/21 | 2025-09-21 17:00 | 52 | 1404/6/29 | 1404/6/30 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي محصول( خانم فرامرز پور) | 0.37735849056603776 | Edit Details Delete |
| 5.6 | آدیت تضمین کیفیت | 0.00208333 | 0.00208333 | 2025/09/22 | 2025-09-22 08:00 | 2025/09/22 | 2025-09-22 17:00 | 53,52 | 1404/6/31 | 1404/6/31 | 0 | 0.0 | 0 | 0 | 0.0 | تضمين كيفيت ( آقاي جلال الديني) | 0.18867924528301888 | Edit Details Delete |
| 5.7 | تست آلايندگي | 0.104167 | 0.104167 | 2025/09/20 | 2025-09-20 08:00 | 2025/11/22 | 2025-11-22 12:00 | 1404/6/29 | 1404/9/1 | 0 | 0.0 | 0 | 0 | 0.0 | 9.433962264150944 | Edit Details Delete | ||
| 5.7.1 | ارسال نمونه به تهران جهت ارسال به كرمان موتور براي انجام تست | 0.00625 | 0.00625 | 2025/09/20 | 2025-09-20 08:00 | 2025/09/22 | 2025-09-22 17:00 | 52 | 1404/6/29 | 1404/6/31 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي محصول كرمان موتور | 0.5660377358490566 | Edit Details Delete |
| 5.7.2 | تست آلايندگي و تست توان سر چرخ نمونه مطالعاتی | 0.09375 | 0.09375 | 2025/09/23 | 2025-09-23 08:00 | 2025/11/18 | 2025-11-18 17:00 | 56 | 1404/7/1 | 1404/8/27 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي محصول كرمان موتور | 8.49056603773585 | Edit Details Delete |
| 5.7.3 | ارسال نتايج به آرمان موتور جهت ثبت در آرشيو فني | 0.00416667 | 0.00416667 | 2025/11/19 | 2025-11-19 08:00 | 2025/11/22 | 2025-11-22 12:00 | 57 | 1404/8/28 | 1404/9/1 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.37735849056603776 | Edit Details Delete |
| 5.8 | فيكسچرهاي توليدي وكنترلي | 0.16875 | 0.16875 | 2025/09/20 | 2025-09-20 08:00 | 2025/12/31 | 2025-12-31 17:00 | 1404/6/29 | 1404/10/10 | 0 | 0.0 | 0 | 0 | 0.0 | 19.62264150943396 | Edit Details Delete | ||
| 5.8.1 | طراحي فيكسچر | 0.0604167 | 0.0604167 | 2025/09/20 | 2025-09-20 08:00 | 2025/10/26 | 2025-10-26 12:00 | 1404/6/29 | 1404/8/4 | 0 | 0.0 | 0 | 0 | 0.0 | 5.471698113207547 | Edit Details Delete | ||
| 5.8.1.1 | اسكن نمونه تائيد شده و مدلسازي | 0.0291667 | 0.0291667 | 2025/09/20 | 2025-09-20 08:00 | 2025/10/06 | 2025-10-06 17:00 | 52 | 1404/6/29 | 1404/7/14 | 0 | 0.0 | 0 | 0 | 0.0 | بازرگاني ( آقايان صفائي / نظري ) | 2.6415094339622645 | Edit Details Delete |
| 5.8.1.2 | طراحي فيكسچر توليدي و كنترلي | 0.0208333 | 0.0208333 | 2025/10/07 | 2025-10-07 08:00 | 2025/10/19 | 2025-10-19 17:00 | 61 | 1404/7/15 | 1404/7/27 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي يوسفيان) | 1.8867924528301887 | Edit Details Delete |
| 5.8.1.3 | اخذ تائيديه براي فيكسچرهاي كنترلي مجموعه نهايي از كادك | 0.0104167 | 0.0104167 | 2025/10/20 | 2025-10-20 08:00 | 2025/10/26 | 2025-10-26 12:00 | 62 | 1404/7/28 | 1404/8/4 | 0 | 0.0 | 0 | 0 | 0.0 | الزامات كادك ( آقاي صالحي) | 0.9433962264150944 | Edit Details Delete |
| 5.8.2 | ساخت فيكسچرتوليدي | 0.0479167 | 0.0479167 | 2025/10/26 | 2025-10-26 13:00 | 2025/11/25 | 2025-11-25 12:00 | 1404/8/4 | 1404/9/4 | 0 | 0.0 | 0 | 0 | 0.0 | 4.339622641509434 | Edit Details Delete | ||
| 5.8.2.1 | ليزر برش قطعات فيكسچر توليدي | 0.03125 | 0.03125 | 2025/10/26 | 2025-10-26 13:00 | 2025/11/13 | 2025-11-13 12:00 | 63 | 1404/8/4 | 1404/8/22 | 0 | 0.0 | 0 | 0 | 0.0 | سازنده مشخص نشده | 2.8301886792452833 | Edit Details Delete |
| 5.8.2.2 | ارسال فيكسچر به بم | 0.00625 | 0.00625 | 2025/11/15 | 2025-11-15 08:00 | 2025/11/17 | 2025-11-17 17:00 | 65 | 1404/8/24 | 1404/8/26 | 0 | 0.0 | 0 | 0 | 0.0 | بازرگاني ( آقاي مرادي),مهندسي پروژه ( آقاي يوسفيان) | 0.5660377358490566 | Edit Details Delete |
| 5.8.2.3 | مونتاژ فيكسچر هاي توليدي در كارخانه | 0.0104167 | 0.0104167 | 2025/11/18 | 2025-11-18 08:00 | 2025/11/25 | 2025-11-25 12:00 | 66 | 1404/8/27 | 1404/9/4 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي ابزار(آقاي ترك پور) | 0.9433962264150944 | Edit Details Delete |
| 5.8.3 | ساخت فيكسچركنترلي | 0.104167 | 0.104167 | 2025/10/26 | 2025-10-26 13:00 | 2025/12/29 | 2025-12-29 17:00 | 1404/8/4 | 1404/10/8 | 0 | 0.0 | 0 | 0 | 0.0 | 9.433962264150944 | Edit Details Delete | ||
| 5.8.3.1 | ساخت فيكسچرهاي كنترلي | 0.09375 | 0.09375 | 2025/10/26 | 2025-10-26 13:00 | 2025/12/23 | 2025-12-23 12:00 | 62,63 | 1404/8/4 | 1404/10/2 | 0 | 0.0 | 0 | 0 | 0.0 | سازنده مشخص نشده | 8.49056603773585 | Edit Details Delete |
| 5.8.3.2 | گزارش گيري ابعادي/ cmm | 0.00416667 | 0.00416667 | 2025/12/23 | 2025-12-23 13:00 | 2025/12/25 | 2025-12-25 12:00 | 69 | 1404/10/2 | 1404/10/4 | 0 | 0.0 | 0 | 0 | 0.0 | سازنده مشخص نشده | 0.37735849056603776 | Edit Details Delete |
| 5.8.3.3 | ارسال فيكسچر به بم | 0.00625 | 0.00625 | 2025/12/27 | 2025-12-27 08:00 | 2025/12/29 | 2025-12-29 17:00 | 70 | 1404/10/6 | 1404/10/8 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي يوسفيان),بازرگاني ( آقاي مرادي) | 0.5660377358490566 | Edit Details Delete |
| 5.8.4 | صورتجلسه تائيد و تحويل فيكسچرها به واحد توليد | 0.00416667 | 0.00416667 | 2025/12/30 | 2025-12-30 08:00 | 2025/12/31 | 2025-12-31 17:00 | 67,71 | 1404/10/9 | 1404/10/10 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي يوسفيان),مهندسي ابزار(آقاي ترك پور) | 0.37735849056603776 | Edit Details Delete |
| 5.9 | پايان فاز | 0 | 0 | 2025/12/31 | 2025-12-31 17:00 | 2025/12/31 | 2025-12-31 17:00 | 52,58,67,63,71,72 | 1404/10/10 | 1404/10/10 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0 | Edit Details Delete | |
| 6 | فاز يك روز خط | 0.18125 | 0.18125 | 2025/09/20 | 2025-09-20 08:00 | 2026/01/08 | 2026-01-08 12:00 | 1404/6/29 | 1404/10/18 | 0 | 0.0 | 0 | 0 | 0.0 | 12.830188679245284 | Edit Details Delete | ||
| 6.1 | سفارش گذاري 100 ست | 0.0104167 | 0.0104167 | 2025/09/20 | 2025-09-20 08:00 | 2025/09/24 | 2025-09-24 17:00 | 49,52 | 1404/6/29 | 1404/7/2 | 0 | 0.0 | 0 | 0 | 0.0 | بازرگاني ( آقايان صفائي / نظري ) | 0.9433962264150944 | Edit Details Delete |
| 6.2 | توليد و ارسال قطعات يك روز خط به كارخانه | 0.0208333 | 0.0208333 | 2025/09/25 | 2025-09-25 08:00 | 2025/10/07 | 2025-10-07 17:00 | 75 | 1404/7/3 | 1404/7/15 | 0 | 0.0 | 0 | 0 | 0.0 | تامين كننده ( ايران اگزوز ) | 1.8867924528301887 | Edit Details Delete |
| 6.3 | آديت فرآيند واحد تضمين كيفيت | 0.00208333 | 0.00208333 | 2025/10/08 | 2025-10-08 08:00 | 2025/10/08 | 2025-10-08 17:00 | 76 | 1404/7/16 | 1404/7/16 | 0 | 0.0 | 0 | 0 | 0.0 | تضمين كيفيت ( آقاي جلال الديني) | 0.18867924528301888 | Edit Details Delete |
| 6.4 | توليد يك روز خط اگزوز در آرمان موتور | 0.00833333 | 0.00833333 | 2025/11/25 | 2025-11-25 13:00 | 2025/11/30 | 2025-11-30 17:00 | 77,76,67 | 1404/9/4 | 1404/9/9 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي توليد /مهندسي پروژه | 0.7547169811320755 | Edit Details Delete |
| 6.5 | ثبت كارتابل يك روز خط و ارسال قطعات به خط توليد كرمان موتور | 0.00625 | 0.00625 | 2025/12/01 | 2025-12-01 08:00 | 2025/12/03 | 2025-12-03 17:00 | 78 | 1404/9/10 | 1404/9/12 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.5660377358490566 | Edit Details Delete |
| 6.6 | مونتاژ يك روز خط-بسته به برنامه توليد | 0.00625 | 0.00625 | 2025/12/04 | 2025-12-04 08:00 | 2025/12/08 | 2025-12-08 12:00 | 79 | 1404/9/13 | 1404/9/17 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي توليد /مهندسي پروژه | 0.5660377358490566 | Edit Details Delete |
| 6.7 | ارزيابي يك روز خط | 0.00833333 | 0.00833333 | 2026/01/01 | 2026-01-01 08:00 | 2026/01/06 | 2026-01-06 12:00 | 80,73 | 1404/10/11 | 1404/10/16 | 0 | 0.0 | 0 | 0 | 0.0 | كادك ( آقاي عبدي) | 0.7547169811320755 | Edit Details Delete |
| 6.8 | تاييديه يك روز خط | 0.00416667 | 0.00416667 | 2026/01/06 | 2026-01-06 13:00 | 2026/01/08 | 2026-01-08 12:00 | 81 | 1404/10/16 | 1404/10/18 | 0 | 0.0 | 0 | 0 | 0.0 | كادك ( آقاي عبدي) | 0.37735849056603776 | Edit Details Delete |
| 6.9 | انجام تست هاي ذكر شده در تست پلن، تهيه تست ريپورت | 0.075 | 0.075 | 2025/11/22 | 2025-11-22 13:00 | 2026/01/07 | 2026-01-07 12:00 | 1404/9/1 | 1404/10/17 | 0 | 0.0 | 0 | 0 | 0.0 | 6.7924528301886795 | Edit Details Delete | ||
| 6.9.1 | دريافت پيش فاكتور از آزمايشگاه | 0.00416667 | 0.00416667 | 2025/11/22 | 2025-11-22 13:00 | 2025/11/25 | 2025-11-25 12:00 | 58 | 1404/9/1 | 1404/9/4 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.37735849056603776 | Edit Details Delete |
| 6.9.2 | پرداخت مبلغ انجام تست | 0.00416667 | 0.00416667 | 2025/11/25 | 2025-11-25 13:00 | 2025/11/27 | 2025-11-27 12:00 | 84 | 1404/9/4 | 1404/9/6 | 0 | 0.0 | 0 | 0 | 0.0 | خزانه ( آقاي محمودي) | 0.37735849056603776 | Edit Details Delete |
| 6.9.3 | ارسال قطعات به ازمايشگاه | 0.00416667 | 0.00416667 | 2025/11/29 | 2025-11-29 08:00 | 2025/11/30 | 2025-11-30 17:00 | 85 | 1404/9/8 | 1404/9/9 | 0 | 0.0 | 0 | 0 | 0.0 | مهندسي پروژه ( آقاي ابراهيم ) | 0.37735849056603776 | Edit Details Delete |
| 6.9.4 | انجام آزمون و تهيه تست ريپورت | 0.0625 | 0.0625 | 2025/12/01 | 2025-12-01 08:00 | 2026/01/07 | 2026-01-07 12:00 | 86 | 1404/9/10 | 1404/10/17 | 0 | 0.0 | 0 | 0 | 0.0 | آزمايشگاه مشخص نيست | 5.660377358490567 | Edit Details Delete |
| 7 | اتمام پروژه- سفارشگذاري جهت توليد انبوه | 0 | 0 | 2026/01/08 | 2026-01-08 12:00 | 2026/01/08 | 2026-01-08 12:00 | 82,83 | 1404/10/18 | 1404/10/18 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0 | Edit Details Delete |