پروژه = T9 Exhaust.mpp

WBS taskname duration duration تاریخ start تاریخ finish predecessors persianstart persianfinish physicalcomplete complete planprogress actualprogress cost resource WF
1 امكان سنجي و توجيه اقتصادي پروژه 20 0 2023/12/27 Dec 27 2023 9:30AM 2024/01/21 Jan 21 2024 12:00PM 2 1402/10/6 1402/11/1 100 0 0 9.75 0 9.75 Edit Details Delete
2 شروع پروژه 0 0 2023/12/27 Dec 27 2023 9:30AM 2023/12/27 Dec 27 2023 9:30AM 1402/10/6 1402/10/6 100 0 0 0 0 0 Edit Details Delete
3 فاز مطالعاتی 27 0 2024/01/21 Jan 21 2024 12:00PM 2024/02/27 Feb 27 2024 10:30AM 1 1402/11/1 1402/12/8 0 0 0 18.12 0 18.12 Edit Details Delete
3.1 دريافت اطلاعات فني از مشتري (نقشه، شناسنامه فني ، تست پلن و ...) 5 0 2024/01/21 Jan 21 2024 12:00PM 2024/01/28 Jan 28 2024 3:00PM 1SS 1402/11/1 1402/11/8 100 0 0 2.44 0 2.44 Edit Details Delete
3.2 دريافت نمونه اگزوز وارداتي (منفصله و مجموعه كامل) 3 0 2024/01/21 Jan 21 2024 12:00PM 2024/01/24 Jan 24 2024 3:31PM 1SS 1402/11/1 1402/11/4 100 0 0 1.55 0 1.55 Edit Details Delete
3.3 انتخاب پيمانكار 5 0 2024/01/21 Jan 21 2024 12:00PM 2024/01/28 Jan 28 2024 3:00PM 1SS 1402/11/1 1402/11/8 100 0 0 2.44 0 2.44 Edit Details Delete
3.4 مذاکره با پیمانکار جهت بررسي و ساخت داخل اگزوز 5 0 2024/01/21 Jan 21 2024 12:00PM 2024/01/28 Jan 28 2024 3:00PM 1SS 1402/11/1 1402/11/8 100 0 0 2.44 0 2.44 Edit Details Delete
3.5 ساخت نمونه مطالعاتی 5 0 2024/01/28 Jan 28 2024 3:00PM 2024/02/04 Feb 4 2024 9:30AM 4,5,6,7 1402/11/8 1402/11/15 100 0 0 2.44 0 2.44 Edit Details Delete
3.6 تست و مونتاژ پذيري نمونه مطالعاتي - بم 2 0 2024/02/04 Feb 4 2024 9:30AM 2024/02/06 Feb 6 2024 10:30AM 8 1402/11/15 1402/11/17 100 0 0 0.97 0 0.97 Edit Details Delete
3.7 تست آلايندگي و تست توان سر چرخ نمونه مطالعاتی 10 0 2024/02/12 Feb 12 2024 12:00PM 2024/02/25 Feb 25 2024 9:30AM 9FS+3 days 1402/11/23 1402/12/6 100 0 0 4.87 0 4.87 Edit Details Delete
3.8 بررسي نتايج تست ها 1 0 2024/02/25 Feb 25 2024 9:30AM 2024/02/26 Feb 26 2024 10:00AM 10 1402/12/6 1402/12/7 100 0 0 0.49 0 0.49 Edit Details Delete
3.9 اخذ تاييدیه یک نمونه از نمونه های مطالعاتی 1 0 2024/02/26 Feb 26 2024 10:00AM 2024/02/27 Feb 27 2024 10:30AM 11 1402/12/7 1402/12/8 100 0 0 0.49 0 0.49 Edit Details Delete
4 فاز توليد و تاييد نمونه اوليه 44 0 2024/02/04 Feb 4 2024 9:30AM 2024/04/17 Apr 17 2024 9:00AM 1402/11/15 1403/1/29 0 0 0 42.4 0 42.4 Edit Details Delete
4.1 توليد 3 ست بعنوان نمونه اوليه 10 0 2024/02/04 Feb 4 2024 9:30AM 2024/02/18 Feb 18 2024 3:00PM 10FS-15 days 1402/11/15 1402/11/29 100 0 0 4.87 0 4.87 Edit Details Delete
4.2 ارسال نمونه هاي اوليه به كارخانه 2 0 2024/02/17 Feb 17 2024 2:30PM 2024/02/19 Feb 19 2024 3:30PM 14FS-1 day 1402/11/28 1402/11/30 100 0 0 0.97 0 0.97 Edit Details Delete
4.3 آدیت تضمین کیفیت 0 0 2024/02/19 Feb 19 2024 3:30PM 2024/02/19 Feb 19 2024 3:30PM 15 1402/11/30 1402/11/30 100 0 0 0 0 0 Edit Details Delete
4.4 بررسي نمونه هاي اوليه توسط واحد مهندسي آرمان موتور 2 0 2024/02/19 Feb 19 2024 3:30PM 2024/02/21 Feb 21 2024 4:30PM 15 1402/11/30 1402/12/2 100 0 0 0.97 0 0.97 Edit Details Delete
4.5 ارسال نمونه هاي اوليه به شركت کرمان موتور 3 0 2024/02/22 Feb 22 2024 8:30AM 2024/02/26 Feb 26 2024 10:00AM 17 1402/12/3 1402/12/7 100 0 0 1.46 0 1.46 Edit Details Delete
4.6 بررسي و ارزيابي نمونه اوليه 4 0 2024/02/26 Feb 26 2024 10:00AM 2024/03/02 Mar 2 2024 12:00PM 18 1402/12/7 1402/12/12 100 0 0 1.95 0 1.95 Edit Details Delete
4.7 اعلام نتايج بررسي نمونه ها 1 0 2024/03/02 Mar 2 2024 12:00PM 2024/03/03 Mar 3 2024 12:30PM 19 1402/12/12 1402/12/13 100 0 0 0.49 0 0.49 Edit Details Delete
4.8 اخذ تاييديه نمونه اوليه 1 0 2024/03/03 Mar 3 2024 1:00PM 2024/03/04 Mar 4 2024 1:30PM 20 1402/12/13 1402/12/14 100 0 0 0.49 0 0.49 Edit Details Delete
4.9 ارسال نمونه تاييد شده به تهران جهت تهيه نقشه 2 0 2024/03/04 Mar 4 2024 1:30PM 2024/03/06 Mar 6 2024 2:30PM 21 1402/12/14 1402/12/16 100 0 0 0.97 0 0.97 Edit Details Delete
4.10 اسكن و مدلسازي 20 0 2024/02/19 Feb 19 2024 3:30PM 2024/03/16 Mar 16 2024 10:00AM 22FS-13 days 1402/11/30 1402/12/26 100 0 0 9.75 0 9.75 Edit Details Delete
4.11 طراحي فيكسچر توليدي و كنترلي 15 0 2024/02/28 Feb 28 2024 11:00AM 2024/03/18 Mar 18 2024 11:00AM 23FS-13 days 1402/12/9 1402/12/28 100 0 0 7.31 0 7.31 Edit Details Delete
4.12 ساخت فيكسچر توليدي و كنترلي 15 0 2024/03/06 Mar 6 2024 2:30PM 2024/04/08 Apr 8 2024 2:30PM 24FS-9 days 1402/12/16 1403/1/20 100 0 0 7.31 0 7.31 Edit Details Delete
4.13 مونتاژ فيكسچر ها در كارخانه 5 0 2024/04/08 Apr 8 2024 2:30PM 2024/04/17 Apr 17 2024 9:00AM 25 1403/1/20 1403/1/29 100 0 0 2.44 0 2.44 Edit Details Delete
4.14 عقد قرارداد توليد اگزوز و سفارش توليد 100 ست 7 0 2024/03/02 Mar 2 2024 12:00PM 2024/03/10 Mar 10 2024 4:00PM 21FS-2 days 1402/12/12 1402/12/20 100 0 0 3.41 0 3.41 Edit Details Delete
5 فاز يك روز خط 41 0 2024/02/27 Feb 27 2024 10:30AM 2024/05/05 May 5 2024 4:30PM 1402/12/8 1403/2/16 0 0 0 27.54 0 29.73 Edit Details Delete
5.1 پيش پرداخت قرارداد 5 0 2024/03/07 Mar 7 2024 3:00PM 2024/03/14 Mar 14 2024 9:30AM 27FS-2 days 1402/12/17 1402/12/24 100 0 0 2.44 0 2.44 Edit Details Delete
5.2 توليد و ارسال قطعات يك روز خط به كارخانه 10 0 2024/03/09 Mar 9 2024 3:30PM 2024/04/04 Apr 4 2024 12:30PM 29FS-4 days 1402/12/19 1403/1/16 100 0 0 4.87 0 4.87 Edit Details Delete
5.3 آديت فرآيند واحد تضمين كيفيت 0 0 2024/04/04 Apr 4 2024 12:30PM 2024/04/04 Apr 4 2024 12:30PM 30 1403/1/16 1403/1/16 0 0 0 0 0 0 Edit Details Delete
5.4 توليد يك روز خط اگزوز در آرمان موتور 4 0 2024/04/14 Apr 14 2024 4:00PM 2024/04/20 Apr 20 2024 10:00AM 31SS,30FS-2 days,26FS-2 days 1403/1/26 1403/2/1 100 0 0 1.95 0 1.95 Edit Details Delete
5.5 مجوز يك روز خط 3 0 2024/04/20 Apr 20 2024 10:00AM 2024/04/23 Apr 23 2024 11:30AM 32 1403/2/1 1403/2/4 50 0 0 0.73 0 1.46 Edit Details Delete
5.6 مونتاژ يك روز خط-بسته به برنامه توليد 3 0 2024/04/23 Apr 23 2024 11:30AM 2024/04/27 Apr 27 2024 1:30PM 33 1403/2/4 1403/2/8 100 0 0 1.46 0 1.46 Edit Details Delete
5.7 انجام تست هاي ذكر شده در تست پلن، تهيه تست ريپورت 30 0 2024/02/27 Feb 27 2024 10:30AM 2024/04/21 Apr 21 2024 10:30AM 21FS-5 days,12FS-5 days 1402/12/8 1403/2/2 90 0 0 13.16 0 14.62 Edit Details Delete
5.8 ارزيابي يك روز خط 4 0 2024/04/27 Apr 27 2024 1:30PM 2024/05/01 May 1 2024 3:30PM 34 1403/2/8 1403/2/12 100 0 0 1.95 0 1.95 Edit Details Delete
5.9 تاييديه يك روز خط 2 0 2024/05/01 May 1 2024 3:30PM 2024/05/05 May 5 2024 4:30PM 36 1403/2/12 1403/2/16 100 0 0 0.97 0 0.97 Edit Details Delete
6 اتمام پروژه- سفارشگذاري جهت توليد انبوه 0 0 2024/05/05 May 5 2024 5:00PM 2024/05/05 May 5 2024 5:00PM 37,35 1403/2/16 1403/2/16 0 0 0 0 0 0 Edit Details Delete
0 Exhaust-T9 88.0d 0.0d 2023/12/27 12/27/2023 12:00:00 AM 2024/05/05 5/5/2024 12:00:00 AM 1402/10/6 1403/2/16 0 0 0 97.8067076043342 0 99.99979693617298 Edit Details Delete
1 امكان سنجي و توجيه اقتصادي پروژه 20.0d 20.0d 2023/12/27 12/27/2023 12:00:00 AM 2024/01/21 1/21/2024 12:00:00 AM 2 1402/10/6 1402/11/1 100 0 0 9.74706369706126 0 9.74706369706126 Edit Details Delete
2 شروع پروژه 0.0d 0.0d 2023/12/27 12/27/2023 12:00:00 AM 2023/12/27 12/27/2023 12:00:00 AM 1402/10/6 1402/10/6 100 0 0 0 0 0 Edit Details Delete
3 فاز مطالعاتی 27.0d 0.0d 2024/01/21 1/21/2024 12:00:00 AM 2024/02/27 2/27/2024 12:00:00 AM 1 1402/11/1 1402/12/8 0 0 0 18.124461880858387 0 18.124461880858387 Edit Details Delete
3.1 دريافت اطلاعات فني از مشتري (نقشه، شناسنامه فني ، تست پلن و ...) 5.0d 5.0d 2024/01/21 1/21/2024 12:00:00 AM 2024/01/28 1/28/2024 12:00:00 AM 1 1402/11/1 1402/11/8 100 0 0 2.436765924265315 0 2.436765924265315 Edit Details Delete
3.2 دريافت نمونه اگزوز وارداتي (منفصله و مجموعه كامل) 3.19d 3.19d 2024/01/21 1/21/2024 12:00:00 AM 2024/01/24 1/24/2024 12:00:00 AM 1 1402/11/1 1402/11/4 100 0 0 1.5544535958542474 0 1.5544535958542474 Edit Details Delete
3.3 انتخاب پيمانكار 5.0d 5.0d 2024/01/21 1/21/2024 12:00:00 AM 2024/01/28 1/28/2024 12:00:00 AM 1 1402/11/1 1402/11/8 100 0 0 2.436765924265315 0 2.436765924265315 Edit Details Delete
3.4 مذاکره با پیمانکار جهت بررسي و ساخت داخل اگزوز 5.0d 5.0d 2024/01/21 1/21/2024 12:00:00 AM 2024/01/28 1/28/2024 12:00:00 AM 1 1402/11/1 1402/11/8 100 0 0 2.436765924265315 0 2.436765924265315 Edit Details Delete
3.5 ساخت نمونه مطالعاتی 5.0d 5.0d 2024/01/28 1/28/2024 12:00:00 AM 2024/02/04 2/4/2024 12:00:00 AM 4,5,6,7 1402/11/8 1402/11/15 100 0 0 2.436765924265315 0 2.436765924265315 Edit Details Delete
3.6 تست و مونتاژ پذيري نمونه مطالعاتي - بم 2.0d 2.0d 2024/02/04 2/4/2024 12:00:00 AM 2024/02/06 2/6/2024 12:00:00 AM 8 1402/11/15 1402/11/17 100 0 0 0.9747063697061259 0 0.9747063697061259 Edit Details Delete
3.7 تست آلايندگي و تست توان سر چرخ نمونه مطالعاتی 10.0d 10.0d 2024/02/12 2/12/2024 12:00:00 AM 2024/02/25 2/25/2024 12:00:00 AM 9 1402/11/23 1402/12/6 100 0 0 4.87353184853063 0 4.87353184853063 Edit Details Delete
3.8 بررسي نتايج تست ها 1.0d 1.0d 2024/02/25 2/25/2024 12:00:00 AM 2024/02/26 2/26/2024 12:00:00 AM 10 1402/12/6 1402/12/7 100 0 0 0.487353184853063 0 0.487353184853063 Edit Details Delete
3.9 اخذ تاييدیه یک نمونه از نمونه های مطالعاتی 1.0d 1.0d 2024/02/26 2/26/2024 12:00:00 AM 2024/02/27 2/27/2024 12:00:00 AM 11 1402/12/7 1402/12/8 100 0 0 0.487353184853063 0 0.487353184853063 Edit Details Delete
4 فاز توليد و تاييد نمونه اوليه 44.0d 0.0d 2024/02/04 2/4/2024 12:00:00 AM 2024/04/17 4/17/2024 12:00:00 AM 1402/11/15 1403/1/29 0 0 0 42.39972708221649 0 42.39972708221649 Edit Details Delete
4.1 توليد 3 ست بعنوان نمونه اوليه 10.0d 10.0d 2024/02/04 2/4/2024 12:00:00 AM 2024/02/18 2/18/2024 12:00:00 AM 10 1402/11/15 1402/11/29 100 0 0 4.87353184853063 0 4.87353184853063 Edit Details Delete
4.2 ارسال نمونه هاي اوليه به كارخانه 2.0d 2.0d 2024/02/17 2/17/2024 12:00:00 AM 2024/02/19 2/19/2024 12:00:00 AM 14 1402/11/28 1402/11/30 100 0 0 0.9747063697061259 0 0.9747063697061259 Edit Details Delete
4.3 آدیت تضمین کیفیت 0.0d 0.0d 2024/02/19 2/19/2024 12:00:00 AM 2024/02/19 2/19/2024 12:00:00 AM 15 1402/11/30 1402/11/30 100 0 0 0 0 0 Edit Details Delete
4.4 بررسي نمونه هاي اوليه توسط واحد مهندسي آرمان موتور 2.0d 2.0d 2024/02/19 2/19/2024 12:00:00 AM 2024/02/21 2/21/2024 12:00:00 AM 15 1402/11/30 1402/12/2 100 0 0 0.9747063697061259 0 0.9747063697061259 Edit Details Delete
4.5 ارسال نمونه هاي اوليه به شركت کرمان موتور 3.0d 3.0d 2024/02/22 2/22/2024 12:00:00 AM 2024/02/26 2/26/2024 12:00:00 AM 17 1402/12/3 1402/12/7 100 0 0 1.462059554559189 0 1.462059554559189 Edit Details Delete
4.6 بررسي و ارزيابي نمونه اوليه 4.0d 4.0d 2024/02/26 2/26/2024 12:00:00 AM 2024/03/02 3/2/2024 12:00:00 AM 18 1402/12/7 1402/12/12 100 0 0 1.9494127394122518 0 1.9494127394122518 Edit Details Delete
4.7 اعلام نتايج بررسي نمونه ها 1.0d 1.0d 2024/03/02 3/2/2024 12:00:00 AM 2024/03/03 3/3/2024 12:00:00 AM 19 1402/12/12 1402/12/13 100 0 0 0.487353184853063 0 0.487353184853063 Edit Details Delete
4.8 اخذ تاييديه نمونه اوليه 1.0d 1.0d 2024/03/03 3/3/2024 12:00:00 AM 2024/03/04 3/4/2024 12:00:00 AM 20 1402/12/13 1402/12/14 100 0 0 0.487353184853063 0 0.487353184853063 Edit Details Delete
4.9 ارسال نمونه تاييد شده به تهران جهت تهيه نقشه 2.0d 2.0d 2024/03/04 3/4/2024 12:00:00 AM 2024/03/06 3/6/2024 12:00:00 AM 21 1402/12/14 1402/12/16 100 0 0 0.9747063697061259 0 0.9747063697061259 Edit Details Delete
4.10 اسكن و مدلسازي 20.0d 20.0d 2024/02/19 2/19/2024 12:00:00 AM 2024/03/16 3/16/2024 12:00:00 AM 22 1402/11/30 1402/12/26 100 0 0 9.74706369706126 0 9.74706369706126 Edit Details Delete
4.11 طراحي فيكسچر توليدي و كنترلي 15.0d 15.0d 2024/02/28 2/28/2024 12:00:00 AM 2024/03/18 3/18/2024 12:00:00 AM 23 1402/12/9 1402/12/28 100 0 0 7.310297772795946 0 7.310297772795946 Edit Details Delete
4.12 ساخت فيكسچر توليدي و كنترلي 15.0d 15.0d 2024/03/06 3/6/2024 12:00:00 AM 2024/04/08 4/8/2024 12:00:00 AM 24 1402/12/16 1403/1/20 100 0 0 7.310297772795946 0 7.310297772795946 Edit Details Delete
4.13 مونتاژ فيكسچر ها در كارخانه 5.0d 5.0d 2024/04/08 4/8/2024 12:00:00 AM 2024/04/17 4/17/2024 12:00:00 AM 25 1403/1/20 1403/1/29 100 0 0 2.436765924265315 0 2.436765924265315 Edit Details Delete
4.14 عقد قرارداد توليد اگزوز و سفارش توليد 100 ست 7.0d 7.0d 2024/03/02 3/2/2024 12:00:00 AM 2024/03/10 3/10/2024 12:00:00 AM 21 1402/12/12 1402/12/20 100 0 0 3.4114722939714412 0 3.4114722939714412 Edit Details Delete
5 فاز يك روز خط 41.0d 0.0d 2024/02/27 2/27/2024 12:00:00 AM 2024/05/05 5/5/2024 12:00:00 AM 1402/12/8 1403/2/16 0 0 0 27.53545494419806 0 29.728544276036846 Edit Details Delete
5.1 پيش پرداخت قرارداد 5.0d 5.0d 2024/03/07 3/7/2024 12:00:00 AM 2024/03/14 3/14/2024 12:00:00 AM 27 1402/12/17 1402/12/24 100 0 0 2.436765924265315 0 2.436765924265315 Edit Details Delete
5.2 توليد و ارسال قطعات يك روز خط به كارخانه 10.0d 10.0d 2024/03/09 3/9/2024 12:00:00 AM 2024/04/04 4/4/2024 12:00:00 AM 29 1402/12/19 1403/1/16 100 0 0 4.87353184853063 0 4.87353184853063 Edit Details Delete
5.3 آديت فرآيند واحد تضمين كيفيت 0.0d 0.0d 2024/04/04 4/4/2024 12:00:00 AM 2024/04/04 4/4/2024 12:00:00 AM 30 1403/1/16 1403/1/16 0 0 0 0 0 0 Edit Details Delete
5.4 توليد يك روز خط اگزوز در آرمان موتور 4.0d 4.0d 2024/04/14 4/14/2024 12:00:00 AM 2024/04/20 4/20/2024 12:00:00 AM 31,30,26 1403/1/26 1403/2/1 100 0 0 1.9494127394122518 0 1.9494127394122518 Edit Details Delete
5.5 مجوز يك روز خط 3.0d 3.0d 2024/04/20 4/20/2024 12:00:00 AM 2024/04/23 4/23/2024 12:00:00 AM 32 1403/2/1 1403/2/4 50 0 0 0.7310297772795945 0 1.462059554559189 Edit Details Delete
5.6 مونتاژ يك روز خط-بسته به برنامه توليد 3.0d 3.0d 2024/04/23 4/23/2024 12:00:00 AM 2024/04/27 4/27/2024 12:00:00 AM 33 1403/2/4 1403/2/8 100 0 0 1.462059554559189 0 1.462059554559189 Edit Details Delete
5.7 انجام تست هاي ذكر شده در تست پلن، تهيه تست ريپورت 30.0d 30.0d 2024/02/27 2/27/2024 12:00:00 AM 2024/04/21 4/21/2024 12:00:00 AM 21,12 1402/12/8 1403/2/2 90 0 0 13.158535991032702 0 14.620595545591891 Edit Details Delete
5.8 ارزيابي يك روز خط 4.0d 4.0d 2024/04/27 4/27/2024 12:00:00 AM 2024/05/01 5/1/2024 12:00:00 AM 34 1403/2/8 1403/2/12 100 0 0 1.9494127394122518 0 1.9494127394122518 Edit Details Delete
5.9 تاييديه يك روز خط 2.0d 2.0d 2024/05/01 5/1/2024 12:00:00 AM 2024/05/05 5/5/2024 12:00:00 AM 36 1403/2/12 1403/2/16 100 0 0 0.9747063697061259 0 0.9747063697061259 Edit Details Delete
6 اتمام پروژه- سفارشگذاري جهت توليد انبوه 0.0d 0.0d 2024/05/05 5/5/2024 12:00:00 AM 2024/05/05 5/5/2024 12:00:00 AM 37,35 1403/2/16 1403/2/16 0 0 0 0 0 0 Edit Details Delete
0 Exhaust-T9 0.183333 0.183333 2023/12/27 2023-12-27 09:30 2024/05/05 2024-05-05 17:00 1402/10/6 1403/2/16 0 0.0 0 0 0.0 99.99979693617298 Edit Details Delete
1 امكان سنجي و توجيه اقتصادي پروژه 0.0416667 0.0416667 2023/12/27 2023-12-27 09:30 2024/01/21 2024-01-21 12:00 2 1402/10/6 1402/11/1 100 0.0 0 0 0.0 9.74706369706126 Edit Details Delete
2 شروع پروژه 0 0 2023/12/27 2023-12-27 09:30 2023/12/27 2023-12-27 09:30 1402/10/6 1402/10/6 100 0.0 0 0 0.0 0.0 Edit Details Delete
3 فاز مطالعاتی 0.05625 0.05625 2024/01/21 2024-01-21 12:00 2024/02/27 2024-02-27 10:30 1 1402/11/1 1402/12/8 0 0.0 0 0 0.0 18.124461880858387 Edit Details Delete
3.1 دريافت اطلاعات فني از مشتري (نقشه، شناسنامه فني ، تست پلن و ...) 0.0104167 0.0104167 2024/01/21 2024-01-21 12:00 2024/01/28 2024-01-28 15:00 1 1402/11/1 1402/11/8 100 0.0 0 0 0.0 2.436765924265315 Edit Details Delete
3.2 دريافت نمونه اگزوز وارداتي (منفصله و مجموعه كامل) 0.00664583 0.00664583 2024/01/21 2024-01-21 12:00 2024/01/24 2024-01-24 15:31 1 1402/11/1 1402/11/4 100 0.0 0 0 0.0 1.5544535958542474 Edit Details Delete
3.3 انتخاب پيمانكار 0.0104167 0.0104167 2024/01/21 2024-01-21 12:00 2024/01/28 2024-01-28 15:00 1 1402/11/1 1402/11/8 100 0.0 0 0 0.0 2.436765924265315 Edit Details Delete
3.4 مذاکره با پیمانکار جهت بررسي و ساخت داخل اگزوز 0.0104167 0.0104167 2024/01/21 2024-01-21 12:00 2024/01/28 2024-01-28 15:00 1 1402/11/1 1402/11/8 100 0.0 0 0 0.0 2.436765924265315 Edit Details Delete
3.5 ساخت نمونه مطالعاتی 0.0104167 0.0104167 2024/01/28 2024-01-28 15:00 2024/02/04 2024-02-04 09:30 4,5,6,7 1402/11/8 1402/11/15 100 0.0 0 0 0.0 2.436765924265315 Edit Details Delete
3.6 تست و مونتاژ پذيري نمونه مطالعاتي - بم 0.00416667 0.00416667 2024/02/04 2024-02-04 09:30 2024/02/06 2024-02-06 10:30 8 1402/11/15 1402/11/17 100 0.0 0 0 0.0 0.9747063697061259 Edit Details Delete
3.7 تست آلايندگي و تست توان سر چرخ نمونه مطالعاتی 0.0208333 0.0208333 2024/02/12 2024-02-12 12:00 2024/02/25 2024-02-25 09:30 9 1402/11/23 1402/12/6 100 0.0 0 0 0.0 4.87353184853063 Edit Details Delete
3.8 بررسي نتايج تست ها 0.00208333 0.00208333 2024/02/25 2024-02-25 09:30 2024/02/26 2024-02-26 10:00 10 1402/12/6 1402/12/7 100 0.0 0 0 0.0 0.487353184853063 Edit Details Delete
3.9 اخذ تاييدیه یک نمونه از نمونه های مطالعاتی 0.00208333 0.00208333 2024/02/26 2024-02-26 10:00 2024/02/27 2024-02-27 10:30 11 1402/12/7 1402/12/8 100 0.0 0 0 0.0 0.487353184853063 Edit Details Delete
4 فاز توليد و تاييد نمونه اوليه 0.0916667 0.0916667 2024/02/04 2024-02-04 09:30 2024/04/17 2024-04-17 09:00 1402/11/15 1403/1/29 0 0.0 0 0 0.0 42.39972708221649 Edit Details Delete
4.1 توليد 3 ست بعنوان نمونه اوليه 0.0208333 0.0208333 2024/02/04 2024-02-04 09:30 2024/02/18 2024-02-18 15:00 10 1402/11/15 1402/11/29 100 0.0 0 0 0.0 4.87353184853063 Edit Details Delete
4.2 ارسال نمونه هاي اوليه به كارخانه 0.00416667 0.00416667 2024/02/17 2024-02-17 14:30 2024/02/19 2024-02-19 15:30 14 1402/11/28 1402/11/30 100 0.0 0 0 0.0 0.9747063697061259 Edit Details Delete
4.3 آدیت تضمین کیفیت 0 0 2024/02/19 2024-02-19 15:30 2024/02/19 2024-02-19 15:30 15 1402/11/30 1402/11/30 100 0.0 0 0 0.0 0.0 Edit Details Delete
4.4 بررسي نمونه هاي اوليه توسط واحد مهندسي آرمان موتور 0.00416667 0.00416667 2024/02/19 2024-02-19 15:30 2024/02/21 2024-02-21 16:30 15 1402/11/30 1402/12/2 100 0.0 0 0 0.0 0.9747063697061259 Edit Details Delete
4.5 ارسال نمونه هاي اوليه به شركت کرمان موتور 0.00625 0.00625 2024/02/22 2024-02-22 08:30 2024/02/26 2024-02-26 10:00 17 1402/12/3 1402/12/7 100 0.0 0 0 0.0 1.462059554559189 Edit Details Delete
4.6 بررسي و ارزيابي نمونه اوليه 0.00833333 0.00833333 2024/02/26 2024-02-26 10:00 2024/03/02 2024-03-02 12:00 18 1402/12/7 1402/12/12 100 0.0 0 0 0.0 1.9494127394122518 Edit Details Delete
4.7 اعلام نتايج بررسي نمونه ها 0.00208333 0.00208333 2024/03/02 2024-03-02 12:00 2024/03/03 2024-03-03 12:30 19 1402/12/12 1402/12/13 100 0.0 0 0 0.0 0.487353184853063 Edit Details Delete
4.8 اخذ تاييديه نمونه اوليه 0.00208333 0.00208333 2024/03/03 2024-03-03 13:00 2024/03/04 2024-03-04 13:30 20 1402/12/13 1402/12/14 100 0.0 0 0 0.0 0.487353184853063 Edit Details Delete
4.9 ارسال نمونه تاييد شده به تهران جهت تهيه نقشه 0.00416667 0.00416667 2024/03/04 2024-03-04 13:30 2024/03/06 2024-03-06 14:30 21 1402/12/14 1402/12/16 100 0.0 0 0 0.0 0.9747063697061259 Edit Details Delete
4.10 اسكن و مدلسازي 0.0416667 0.0416667 2024/02/19 2024-02-19 15:30 2024/03/16 2024-03-16 10:00 22 1402/11/30 1402/12/26 100 0.0 0 0 0.0 9.74706369706126 Edit Details Delete
4.11 طراحي فيكسچر توليدي و كنترلي 0.03125 0.03125 2024/02/28 2024-02-28 11:00 2024/03/18 2024-03-18 11:00 23 1402/12/9 1402/12/28 100 0.0 0 0 0.0 7.310297772795946 Edit Details Delete
4.12 ساخت فيكسچر توليدي و كنترلي 0.03125 0.03125 2024/03/06 2024-03-06 14:30 2024/04/08 2024-04-08 14:30 24 1402/12/16 1403/1/20 100 0.0 0 0 0.0 7.310297772795946 Edit Details Delete
4.13 مونتاژ فيكسچر ها در كارخانه 0.0104167 0.0104167 2024/04/08 2024-04-08 14:30 2024/04/17 2024-04-17 09:00 25 1403/1/20 1403/1/29 100 0.0 0 0 0.0 2.436765924265315 Edit Details Delete
4.14 عقد قرارداد توليد اگزوز و سفارش توليد 100 ست 0.0145833 0.0145833 2024/03/02 2024-03-02 12:00 2024/03/10 2024-03-10 16:00 21 1402/12/12 1402/12/20 100 0.0 0 0 0.0 3.4114722939714412 Edit Details Delete
5 فاز يك روز خط 0.0854167 0.0854167 2024/02/27 2024-02-27 10:30 2024/05/05 2024-05-05 16:30 1402/12/8 1403/2/16 0 0.0 0 0 0.0 29.728544276036846 Edit Details Delete
5.1 پيش پرداخت قرارداد 0.0104167 0.0104167 2024/03/07 2024-03-07 15:00 2024/03/14 2024-03-14 09:30 27 1402/12/17 1402/12/24 100 0.0 0 0 0.0 2.436765924265315 Edit Details Delete
5.2 توليد و ارسال قطعات يك روز خط به كارخانه 0.0208333 0.0208333 2024/03/09 2024-03-09 15:30 2024/04/04 2024-04-04 12:30 29 1402/12/19 1403/1/16 100 0.0 0 0 0.0 4.87353184853063 Edit Details Delete
5.3 آديت فرآيند واحد تضمين كيفيت 0 0 2024/04/04 2024-04-04 12:30 2024/04/04 2024-04-04 12:30 30 1403/1/16 1403/1/16 0 0.0 0 0 0.0 0.0 Edit Details Delete
5.4 توليد يك روز خط اگزوز در آرمان موتور 0.00833333 0.00833333 2024/04/14 2024-04-14 16:00 2024/04/20 2024-04-20 10:00 31,30,26 1403/1/26 1403/2/1 100 0.0 0 0 0.0 1.9494127394122518 Edit Details Delete
5.5 مجوز يك روز خط 0.00625 0.00625 2024/04/20 2024-04-20 10:00 2024/04/23 2024-04-23 11:30 32 1403/2/1 1403/2/4 50 0.0 0 0 0.0 1.462059554559189 Edit Details Delete
5.6 مونتاژ يك روز خط-بسته به برنامه توليد 0.00625 0.00625 2024/04/23 2024-04-23 11:30 2024/04/27 2024-04-27 13:30 33 1403/2/4 1403/2/8 100 0.0 0 0 0.0 1.462059554559189 Edit Details Delete
5.7 انجام تست هاي ذكر شده در تست پلن، تهيه تست ريپورت 0.0625 0.0625 2024/02/27 2024-02-27 10:30 2024/04/21 2024-04-21 10:30 21,12 1402/12/8 1403/2/2 90 0.0 0 0 0.0 14.620595545591891 Edit Details Delete
5.8 ارزيابي يك روز خط 0.00833333 0.00833333 2024/04/27 2024-04-27 13:30 2024/05/01 2024-05-01 15:30 34 1403/2/8 1403/2/12 100 0.0 0 0 0.0 1.9494127394122518 Edit Details Delete
5.9 تاييديه يك روز خط 0.00416667 0.00416667 2024/05/01 2024-05-01 15:30 2024/05/05 2024-05-05 16:30 36 1403/2/12 1403/2/16 100 0.0 0 0 0.0 0.9747063697061259 Edit Details Delete
6 اتمام پروژه- سفارشگذاري جهت توليد انبوه 0 0 2024/05/05 2024-05-05 17:00 2024/05/05 2024-05-05 17:00 37,35 1403/2/16 1403/2/16 0 0.0 0 0 0.0 0.0 Edit Details Delete